United States โ€บ Grid โ€บ Interconnection queues โ€บ Pennsylvania

OCTARY USA ยท INTERCONNECTION QUEUES

Projects with signed interconnection agreements in Pennsylvania

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown582,306 MW
Active in queue12.5 GW231 requests
Agreement signed2,306 MW58 requests
Withdrawn1,354164.3 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

58 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
French Creek Solar and BESS
Solar + storage ยท French Creek Energy, LLC
150 MWAgreement signed Erie, PAPJM Sep 2020target 2029
Ridgeway Solar
Solar
120 MWAgreement signed Mckean, PAPJM Mar 2019target 2026
Hoodlebug Solar Energy Center
Solar
110 MWAgreement signed Indiana, PAPJM Oct 2019target 2027
Rogue's Wind
Onshore wind
110 MWAgreement signed Clearfield, PAPJM Aug 2019target 2026
Bradford Solar
Solar
101 MWAgreement signed Mckean, PAPJM Mar 2019target 2027
Rockdale Solar
Solar
100 MWAgreement signed Somerset, PAPJM Sep 2019target 2028
Black Moshannon Solar
Solar + storage ยท CE-Black Moshannon OZ LLC
95.0 MWAgreement signed Centre, PAPJM Aug 2020target 2023
Squab Solar
Solar
90.0 MWAgreement signed Jefferson, PAPJM Mar 2019target 2027
MPG Solar
Solar
83.6 MWAgreement signed Centre, PAPJM Mar 2019target 2028
Wilson Solar
Solar
80.0 MWAgreement signed Erie, PAPJM Aug 2019target 2028
Walker Solar Two
Solar
80.0 MWAgreement signed Juniata, PAPJM Mar 2020target 2026
Swiftwater Solar
Solar
80.0 MWAgreement signed Monroe, PAPJM Mar 2019target 2025
MPG Solar
Solar
78.4 MWAgreement signed Centre, PAPJM Mar 2019target 2028
Mora Solar
Solar
60.0 MWAgreement signed Carbon, PAPJM Sep 2020target 2027
MC Solar I
Solar
50.0 MWAgreement signed Mercer, PAPJM Mar 2019target 2027
Peach Bottom Units #2 & #3
Nuclear
44.0 MWAgreement signed York, PAPJM Apr 20162019
Solar project AF1-302, Jefferson County
Solar
42.0 MWAgreement signed Jefferson, PAPJM Sep 2019target 2027
Washington West Solar
Solar + storage
40.0 MWAgreement signed Snyder, PAPJM Mar 2020target 2026
Green Meadows Solar
Solar
40.0 MWAgreement signed Lawrence, PAPJM Jul 2020target 2027
Potter Solar
Solar
35.0 MWAgreement signed Potter, PAPJM Feb 2019target 2026
Farmers Valley Solar
Solar
20.0 MWAgreement signed Bradford, PAPJM Mar 2020target 2028
Franklin Solar
Solar
20.0 MWAgreement signed Crawford, PAPJM Aug 2019target 2026
FR-Williamsport
Solar
20.0 MWAgreement signed Franklin, PAPJM Sep 2019target 2025
Frosty Valley Energy Center
Solar
20.0 MWAgreement signed Columbia, PAPJM Mar 2020target 2027
Club Ford Energy Center
Solar
20.0 MWAgreement signed Adams, PAPJM Apr 2020target 2028
CL-Green Acres
Solar
20.0 MWAgreement signed Clearfield, PAPJM Sep 2019target 2028
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
WA-Cochecton 2
Solar
20.0 MWAgreement signed Adams, PAPJM Mar 2020target 2027
Jackson Center Solar Facility
Solar
20.0 MWAgreement signed Mercer, PAPJM Sep 2018target 2026
Shamrock Energy Center
Solar
20.0 MWAgreement signed Northumberland, PAPJM Mar 2020target 2027
Fayette Energy Facility
Battery storage
20.0 MWAgreement signed Fayette, PAPJM Oct 2019target 2028
Ontelaunee Power Generating Plant
Battery storage
20.0 MWAgreement signed Berks, PAPJM Oct 2019target 2029
Shamrock Energy Center
Solar
20.0 MWAgreement signed Adams, PAPJM Mar 2020target 2027
BL-Hileman Hollow
Solar
20.0 MWAgreement signed Blair, PAPJM Sep 2020target 2027
Gobbler Knob
Solar
20.0 MWAgreement signed Cumberland, PAPJM Mar 2020target 2027
Nichols Solar
Solar
20.0 MWAgreement signed Crawford, PAPJM Jun 2020target 2026
Black Moshannon Solar
Solar ยท CE-Black Moshannon OZ LLC
20.0 MWAgreement signed Centre, PAPJM Sep 2020target 2023
Washington East Solar
Solar + storage
20.0 MWAgreement signed Snyder, PAPJM Mar 2020target 2026
Club Ford Energy Center
Solar
20.0 MWAgreement signed Luzerne, PAPJM Sep 2020target 2027
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
UN-Kylertown
Solar
20.0 MWAgreement signed Westmoreland, PAPJM Feb 2019target 2027
Limestone Solar
Solar
20.0 MWAgreement signed Union, PAPJM Sep 2019target 2027
Jackson Center Solar II
Solar
20.0 MWAgreement signed Mercer, PAPJM Aug 2019target 2026
Henry Solar
Solar
20.0 MWAgreement signed Crawford, PAPJM Aug 2020target 2027
Club Ford Energy Center
Solar
20.0 MWAgreement signed Luzerne, PAPJM Sep 2020target 2027
CL- Belsena Solar
Solar ยท CL-Belsena LLC
20.0 MWAgreement signed Clearfield, PAPJM Mar 2020target 2028
Black Moshannon Solar
Solar ยท CE-Black Moshannon OZ LLC
20.0 MWAgreement signed Centre, PAPJM Sep 2020target 2023
Welcome Solar II
Solar + storage
19.9 MWAgreement signed Crawford, PAPJM Sep 2018target 2026
Welcome Solar, LLC
Solar + storage
19.9 MWAgreement signed Mercer, PAPJM Aug 2018target 2027
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)