SOLAR + STORAGE · PJM

Washington East Solar

Washington East Solar is a 20.0 MW solar + storage request with a signed interconnection agreement in the PJM interconnection queue, in Snyder County, Pennsylvania, connecting to PPL.

Queue statusConsented
  1. PlanningQueued Mar 2020 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
AF2-233
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
PPL
Connection point (POI)
Penns-Richfield Tie #1 69 kV
Location
Snyder County, Pennsylvania
Technology
Solar: 20.0 MW · Battery
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Active
Entered queue
26 March 2020
Proposed online date
December 2026

Location

Marker shows the centre of Snyder County; the queue data does not give exact sites.

Power plants in Pennsylvania · Transmission lines in Pennsylvania