SOLAR · PJMGobbler Knob
Gobbler Knob is a 20.0 MW solar request with a signed interconnection agreement in the PJM interconnection queue, in Cumberland County, Pennsylvania, connecting to PENELEC.
Queue statusConsented
- PlanningQueued Mar 2020 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2027 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- AF2-229
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- PENELEC
- Connection point (POI)
- Roxbury 23 kV
- Location
- Cumberland County, Pennsylvania
- Technology
- Solar: 20.0 MW
- Total requested
- 20.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Active
- Entered queue
- 26 March 2020
- Proposed online date
- November 2027
Location
Marker shows the centre of Cumberland County; the queue data does not give exact sites.
Power plants in Pennsylvania · Transmission lines in Pennsylvania
Other requests in Cumberland County
- Solar project AG2-166, Cumberland CountySolar · 10.0 MW · in study
- Cumberland County LFOther · 6.4 MW · built
- Cumberland County LandfillOther · 4.8 MW · built
- Mountain Station Unit C2Gas · 1.0 MW · built
- Solar project W3-068, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project AE2-252, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project W2-096, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project X2-004, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project X2-005, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project X4-010, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project Y2-061, Cumberland CountySolar · 20.0 MW · withdrawn
- Solar project W3-069, Cumberland CountySolar · 20.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem