OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in Ohio (2020 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Grange Solar Solar |
500 MW | Withdrawn / abandoned |
| Grange Solar Solar + storage |
400 MW | Withdrawn / abandoned |
| Battery storage project AG1-199, Lucas County Battery storage ยท Occasio Power Management LLC |
300 MW | Withdrawn / abandoned |
| Solar project AG2-053, Fulton County Solar ยท Orchid Acres Solar Project, LLC |
300 MW | Withdrawn / abandoned |
| Solar project AG1-408, Fulton County Solar |
300 MW | Withdrawn / abandoned |
| Taylor Creek Solar |
250 MW | Withdrawn / abandoned |
| Solar project AG1-218, Union County Solar |
250 MW | Withdrawn / abandoned |
| Solar project AF2-217, Union County Solar |
220 MW | Withdrawn / abandoned |
| Solar project AF2-210, Pickaway County Solar |
200 MW | Withdrawn / abandoned |
| Solar project AF2-223, Union County Solar |
200 MW | Withdrawn / abandoned |
| Grange Solar Battery storage |
200 MW | Withdrawn / abandoned |
| Solar project AG2-013, Logan County Solar |
200 MW | Withdrawn / abandoned |
| Solar project AF2-079, Darke County Solar |
165 MW | Withdrawn / abandoned |
| Stark Solar Solar |
150 MW | Withdrawn / abandoned |
| Solar project AF2-216, Union County Solar |
150 MW | Withdrawn / abandoned |
| Solar project AF2-321, Williams County Solar ยท Williams County Solar, LLC |
148 MW | Withdrawn / abandoned |
| Solar project AF2-209, Defiance County Solar ยท Mink Solar LLC |
140 MW | Withdrawn / abandoned |
| Solar project AF2-124, Highland County Solar |
120 MW | Withdrawn / abandoned |
| Solar project AG2-018, Morgan County Solar |
105 MW | Withdrawn / abandoned |
| Solar project AG1-042, Franklin County Solar |
100 MW | Withdrawn / abandoned |
| Ripley Solar II Solar |
100 MW | Withdrawn / abandoned |
| Solar project AG1-328, Union County Solar |
100 MW | Withdrawn / abandoned |
| Battery storage project AG2-054, Fulton County Battery storage ยท Orchid Acres Solar Project, LLC |
100 MW | Withdrawn / abandoned |
| Solar project AF2-369, Union County Solar |
100 MW | Withdrawn / abandoned |
| Solar project AF2-263, Shelby County Solar ยท AEUG Shelby Solar, LLC |
98.0 MW | Withdrawn / abandoned |
| Solar + storage project AG1-380, Jackson County Solar + storage |
90.0 MW | Withdrawn / abandoned |
| Solar project AG1-249, Union County Solar |
80.0 MW | Withdrawn / abandoned |
| Solar project AF2-066, Preble County Solar |
80.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-113, Clinton County Battery storage |
75.0 MW | Withdrawn / abandoned |
| Solar project AG1-122, Madison County Solar |
70.0 MW | Withdrawn / abandoned |
| Solar project AG1-319, Henry County Solar ยท CG Henry County LLC |
65.0 MW | Withdrawn / abandoned |
| Solar project AG1-161, Coshocton County Solar |
58.9 MW | Withdrawn / abandoned |
| Solar project AG1-358, Crawford County Solar |
58.0 MW | Withdrawn / abandoned |
| Solar project AG1-530, Clark County Solar |
54.0 MW | Withdrawn / abandoned |
| Solar project AG1-056, Williams County Solar |
54.0 MW | Withdrawn / abandoned |
| Solar project AF2-218, Darke County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project AG2-006, Licking County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project AG1-068, Adams County Solar |
49.9 MW | Withdrawn / abandoned |
| Solar project AF2-123, Madison County Solar |
49.0 MW | Withdrawn / abandoned |
| Solar project AF2-186, Paulding County Solar |
45.0 MW | Withdrawn / abandoned |
| Solar project AF2-084, Union County Solar |
42.0 MW | Withdrawn / abandoned |
| Bellefontaine PV and BESS Project Solar + storage ยท Hodson GreenDefine Blue Jacket LLC |
40.0 MW | Withdrawn / abandoned |
| Solar project AF2-067, Preble County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project AF2-127, Defiance County Solar |
38.0 MW | Withdrawn / abandoned |
| Solar project AG2-031, Stark County Solar |
30.2 MW | Withdrawn / abandoned |
| Battery storage project AG1-456, Highland County Battery storage ยท Willowbrook Solar I, LLC |
30.0 MW | Withdrawn / abandoned |
| Battery storage project AF2-198, Licking County Battery storage |
22.4 MW | Withdrawn / abandoned |
| Solar project AF2-059, Auglaize County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG2-033, Auglaize County Solar |
20.0 MW | Withdrawn / abandoned |
| Solar project AG1-231, Greene County Solar |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)