United States βΊ Grid βΊ Interconnection queues βΊ Ohio
SOLAR Β· PJMStark Solar
Stark Solar is a 150 MW solar request withdrawn in the PJM interconnection queue, in Stark County, Ohio, connecting to ATSI.
Queue statusWithdrawn / abandoned
- PlanningQueued Sep 2020 (completed)
- Withdrawn / abandonedApr 2025 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AG1-239
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- ATSI
- Connection point (POI)
- Blue Bell-Canton Central 138 kV
- Location
- Stark County, Ohio
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Withdrawn
- Entered queue
- 25 September 2020
- Proposed online date
- December 2028
- Withdrawn
- April 2025
Location
Marker shows the centre of Stark County; the queue data does not give exact sites.
Other requests in Stark County
- Battery storage project AH1-752, Stark CountyBattery storage Β· 400 MW Β· withdrawn
- Solar project AH1-655, Stark CountySolar Β· 100 MW Β· withdrawn
- Solar project AH1-350, Stark CountySolar Β· 92.4 MW Β· withdrawn
- Solar project AG2-031, Stark CountySolar Β· 30.2 MW Β· withdrawn
- Robertsville PV ISolar Β· 19.7 MW Β· withdrawn
- Bolivar SolarSolar Β· 19.3 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem