United States โ€บ Grid โ€บ Interconnection queues โ€บ Missouri

OCTARY USA ยท INTERCONNECTION QUEUES

Queue requests in study in Missouri

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown8520.6 GW
Active in queue29.7 GW124 requests
Agreement signed7,888 MW34 requests
Withdrawn25251.8 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

85 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project J3996, St. Charles County
Gas
2,220 MWIn study St. Charles, MOMISO Apr 2025target 2030
Replacing 864 MW of coal with Natural Gas Generators; Castle Bluff
Gas
824 MWIn study St. Louis, MOMISO May 2024target 2025
Gas project GEN-2024-207, Jackson County
Gas
779 MWIn study Jackson, MOSPP Mar 2025target 2029
Onshore wind project GI-122, Randolph County
Onshore wind
500 MWIn study Randolph, MOSoutheast May 2024target 2028
Gas project GI-132, Butler County
Gas
460 MWIn study Butler, MOSoutheast Jul 2025target 2030
Gas project GI-131, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jul 2025target 2030
Gas project GI-126, Randolph County
Gas
460 MWIn study Randolph, MOSoutheast Jan 2025target 2029
Gas project GI-128, Clinton County
Gas
460 MWIn study Clinton, MOSoutheast Jul 2025target 2030
Gas project ERAS-2025-007, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Oct 2025target 2030
Gas project ERAS-2025-013, Nodaway County
Gas
451 MWIn study Nodaway, MOSPP Sep 2025target 2030
Battery storage project GEN-2025-SR1, Henry County
Battery storage
400 MWIn study Henry, MOSPP Apr 2025target 2027
Solar project GEN-2024-289, Henry County
Solar
350 MWIn study Henry, MOSPP Mar 2025target 2029
Solar project E0013, Sullivan County
Solar ยท Union Electric Company d/b/a Ameren Missouri
310 MWIn study Sullivan, MOMISO Aug 2025target 2028
Solar project J3957, Sullivan County
Solar
300 MWIn study Sullivan, MOMISO Apr 2025target 2029
Battery storage project J3518, Gasconade County
Battery storage
300 MWIn study Gasconade, MOMISO Apr 2024target 2028
Solar + storage project J2205, Callaway County
Solar + storage
300 MWIn study Callaway, MOMISO Aug 2021target 2024
Solar project J1836, Callaway County
Solar
300 MWIn study Callaway, MOMISO Jun 2020target 2025
Solar + storage project J3199, Adair County
Solar + storage
300 MWIn study Adair, MOMISO Sep 2022target 2026
Solar project J3758, Macon County
Solar
300 MWIn study Macon, MOMISO Apr 2024target 2028
Battery storage project GEN-2022-073, Clay County
Battery storage
300 MWIn study Clay, MOSPP Sep 2022target 2030
Battery storage project GEN-2024-170, Cass County
Battery storage
280 MWIn study Cass, MOSPP Mar 2025target 2028
Battery storage project E0017, Lincoln County
Battery storage ยท Union Electric Company d/b/a Ameren Missouri
258 MWIn study Lincoln, MOMISO Aug 2025target 2028
Battery storage project J3352, Cape Girardeau County
Battery storage
250 MWIn study Cape Girardeau, MOMISO Apr 2024target 2027
Other project J2691, Bollinger County
Other
250 MWIn study Bollinger, MOMISO Sep 2022target 2027
Gas project ERAS-2025-034, Jasper County
Gas
250 MWIn study Jasper, MOSPP Sep 2025target 2030
Onshore wind project J3929, Audrain County
Onshore wind
250 MWIn study Audrain, MOMISO Jan 2025target 2030
Battery storage project GEN-2024-217, Jackson County
Battery storage
250 MWIn study Jackson, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-370, Clay County
Battery storage
250 MWIn study Clay, MOSPP Mar 2025target 2028
Solar project J4001, Marion County
Solar
245 MWIn study Marion, MOMISO Apr 2025target 2030
Gas project GEN-2024-206, Jackson County
Gas
226 MWIn study Jackson, MOSPP Mar 2025target 2026
Solar project J2050, Macon County
Solar
208 MWIn study Macon, MOMISO Mar 2022target 2024
Solar project J2524, Stoddard County
Solar
200 MWIn study Stoddard, MOMISO Sep 2022target 2026
Battery storage project GEN-2022-142, Clay County
Battery storage
200 MWIn study Clay, MOSPP Feb 2023target 2030
Surplus; J944
Battery storage
200 MWIn study New Madrid, MOMISO Aug 2025target 2028
Solar + storage project J2238, Maries County
Solar + storage
200 MWIn study Maries, MOMISO Jul 2025target 2024
Solar + storage project J2265, Bollinger County
Solar + storage
200 MWIn study Bollinger, MOMISO Jul 2025target 2024
Battery storage project GEN-2022-144, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Feb 2023target 2030
Solar project J3919, Lincoln County
Solar
200 MWIn study Lincoln, MOMISO Mar 2025target 2030
Solar project J2806, Warren County
Solar
200 MWIn study Warren, MOMISO Sep 2022target 2026
Battery storage project GEN-2024-074, Jackson County
Battery storage
200 MWIn study Jackson, MOSPP Oct 2024target 2028
Battery storage project J3440, Daviess County
Battery storage
200 MWIn study Daviess, MOMISO Apr 2024target 2028
Solar project J3959, Grundy County
Solar
200 MWIn study Grundy, MOMISO Apr 2025target 2029
Solar project J4090, Schuyler County
Solar
200 MWIn study Schuyler, MOMISO Oct 2025target 2030
Battery storage project GEN-2023-033, Clay County
Battery storage
200 MWIn study Clay, MOSPP Oct 2023target 2028
Solar project J1519, Bollinger County
Solar
200 MWIn study Bollinger, MOMISO Jun 2020target 2025
Battery storage project GEN-2024-175, Greene County
Battery storage
200 MWIn study Greene, MOSPP Mar 2025target 2028
Solar project J3436, Daviess County
Solar
200 MWIn study Daviess, MOMISO Apr 2024target 2028
Solar + storage project GEN-2024-259, Barton County
Solar + storage
200 MWIn study Barton, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-260, Buchanan County
Battery storage
200 MWIn study Buchanan, MOSPP Mar 2025target 2029
Battery storage project GEN-2024-352, Jackson County
Battery storage
199 MWIn study Jackson, MOSPP Mar 2025target 2030
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)