Onshore wind interconnection queue in Iowa

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown367,291 MW
Active in queue7,291 MW36 requests
Agreement signed967 MW5 requests
Withdrawn18334.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

36 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J3701, Taylor County
Onshore wind
400 MWIn study Taylor, IAMISO Apr 2024target 2028
Onshore wind project E0015, Franklin County
Onshore wind Β· Interstate Power and Light Company (IPL)
360 MWIn study Franklin, IAMISO Aug 2025target 2028
Onshore wind project J3798, Winnebago County
Onshore wind
320 MWIn study Winnebago, IAMISO Mar 2024target 2028
Onshore wind project J4056, Marshall County
Onshore wind
310 MWIn study Marshall, IAMISO Aug 2025target 2030
Onshore wind project J2369, Taylor County
Onshore wind
300 MWIn study Taylor, IAMISO Sep 2022target 2030
Onshore wind project J982, Dickinson County
Onshore wind
300 MWAgreement signed Dickinson, IAMISO Mar 2018target 2024
Onshore wind project J2436, Webster County
Onshore wind
300 MWIn study Webster, IAMISO Sep 2022target 2030
Onshore wind project J4006, Ringgold County
Onshore wind
290 MWIn study Ringgold, IAMISO May 2025target 2030
Onshore wind project J1432, Clinton County
Onshore wind
250 MWAgreement signed Clinton, IAMISO Apr 2019target 2025
Onshore wind project J4068, Marshall County
Onshore wind
232 MWIn study Marshall, IAMISO Oct 2025target 2030
Onshore wind project J2342, Worth County
Onshore wind
230 MWIn study Worth, IAMISO Sep 2022target 2027
Onshore wind project J1590, Plymouth County
Onshore wind
200 MWIn study Plymouth, IAMISO Jun 2024target 2026
Onshore wind project J1867, Franklin County
Onshore wind
200 MWIn study Franklin, IAMISO Nov 2021target 2025
Onshore wind project J3324, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2024target 2029
Onshore wind project J2990, Pottawattamie County
Onshore wind
200 MWIn study Pottawattamie, IAMISO Sep 2022target 2025
Onshore wind project J3849, Winnebago County
Onshore wind
200 MWIn study Winnebago, IAMISO Dec 2024target 2030
Onshore wind project J3713, Wapello County
Onshore wind
200 MWIn study Wapello, IAMISO Apr 2024target 2028
Onshore wind project J3655, Dallas County
Onshore wind
200 MWIn study Dallas, IAMISO Apr 2024target 2028
Onshore wind project J1270, Palo Alto County
Onshore wind
200 MWIn study Palo Alto, IAMISO Apr 2019target 2024
Onshore wind project J2989, Hardin County
Onshore wind
200 MWIn study Hardin, IAMISO Sep 2022target 2025
Onshore wind project J3157, Winnebago County
Onshore wind
200 MWIn study Winnebago, IAMISO Sep 2022target 2024
Onshore wind project J3702, Mitchell County
Onshore wind
180 MWIn study Mitchell, IAMISO Mar 2024target 2028
Onshore wind project GEN-2017-222, Crawford County
Onshore wind
180 MWAgreement signed Crawford, IASPP Nov 2017target 2027
Onshore wind project J2988, Humboldt County
Onshore wind
175 MWIn study Humboldt, IAMISO Sep 2022target 2025
Onshore wind project J3926, Webster County
Onshore wind
170 MWIn study Webster, IAMISO Mar 2025target 2030
Onshore wind project J1365, Tama County
Onshore wind
169 MWIn study Tama, IAMISO Apr 2019target 2024
Onshore wind project J1175, Worth County
Onshore wind
165 MWAgreement signed Worth, IAMISO Mar 2018target 2024
Onshore wind project J2576, Louisa County
Onshore wind
164 MWIn study Louisa, IAMISO Sep 2022target 2025
Onshore wind project J3898, Howard County
Onshore wind
155 MWIn study Howard, IAMISO Feb 2025target 2030
Onshore wind project J2686, Muscatine County
Onshore wind
150 MWIn study Muscatine, IAMISO Sep 2022target 2026
Onshore wind project J1769, Howard County
Onshore wind
120 MWIn study Howard, IAMISO Jun 2020target 2026
Onshore wind project J2031, Tama County
Onshore wind
100 MWIn study Tama, IAMISO Aug 2021target 2026
Onshore wind project J898, Howard County
Onshore wind
100 MWUnder construction Howard, IAMISO Jun 2017target 2023
Onshore wind project GEN-2018-074, Crawford County
Onshore wind
72.0 MWAgreement signed Crawford, IASPP Oct 2018target 2028
Onshore wind project J1998, Franklin County
Onshore wind
66.0 MWIn study Franklin, IAMISO Aug 2021target 2024
Onshore wind project J2122, Franklin County
Onshore wind
33.0 MWIn study Franklin, IAMISO Aug 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)