United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Iowa (2021 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown193,622 MW
Active in queue1,882 MW15 requests
Agreement signed0.0 MW0 requests
Withdrawn193,622 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

19 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Replace 15 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
640 MWWithdrawn / abandoned Linn, IAMISO Sep 2021target 2023
Onshore wind project J1865, Hardin County
Onshore wind
250 MWWithdrawn / abandoned Hardin, IAMISO Aug 2021target 2024
Onshore wind project J1864, Cerro Gordo County
Onshore wind
250 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2021target 2024
Battery storage project J2095, Tama County
Battery storage
212 MWWithdrawn / abandoned Tama, IAMISO Aug 2021target 2024
Battery storage project J2105, Franklin County
Battery storage
200 MWWithdrawn / abandoned Franklin, IAMISO Aug 2021target 2024
Solar project J2166, Taylor County
Solar
200 MWWithdrawn / abandoned Taylor, IAMISO Aug 2021target 2025
Onshore wind project J1979, Howard County
Onshore wind
200 MWWithdrawn / abandoned Howard, IAMISO Aug 2021target 2025
Onshore wind project J1859, Pottawattamie County
Onshore wind
200 MWWithdrawn / abandoned Pottawattamie, IAMISO Aug 2021target 2024
Onshore wind project J1952, Cerro Gordo County
Onshore wind
180 MWWithdrawn / abandoned Cerro Gordo, IAMISO Aug 2021target 2024
Onshore wind project J1978, Pocahontas County
Onshore wind
175 MWWithdrawn / abandoned Pocahontas, IAMISO Aug 2021target 2025
Onshore wind project J2106, Story County
Onshore wind
150 MWWithdrawn / abandoned Story, IAMISO Aug 2021target 2024
Onshore wind project J2079, Hancock County
Onshore wind
150 MWWithdrawn / abandoned Hancock, IAMISO Aug 2021target 2024
Onshore wind project J2040, Dickinson County
Onshore wind
150 MWWithdrawn / abandoned Dickinson, IAMISO Aug 2021target 2024
Onshore wind project J2256, Humboldt County
Onshore wind
150 MWWithdrawn / abandoned Humboldt, IAMISO Aug 2021target 2024
Solar project J2108, Johnson County
Solar
150 MWWithdrawn / abandoned Johnson, IAMISO Aug 2021target 2024
Onshore wind project J1903, Osceola County
Onshore wind
140 MWWithdrawn / abandoned Osceola, IAMISO Aug 2021target 2024
Solar project J1972, Des Moines County
Solar
115 MWWithdrawn / abandoned Des Moines, IAMISO Aug 2021target 2025
Replace 60 MW of ALTW.FPL_DAEC Unit with Battery; Duane Arnold
Other
60.0 MWWithdrawn / abandoned Linn, IAMISO Mar 2021target 2023
Battery storage project J1853, Des Moines County
Battery storage
50.0 MWWithdrawn / abandoned Des Moines, IAMISO Aug 2021target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)