Solar project J2166, Taylor County

Solar project J2166, Taylor County is a 200 MW solar request withdrawn in the MISO interconnection queue, in Taylor County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2166
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
Clarinda - Braddyville 161 kV line
Location
Taylor County, Iowa
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
17 August 2021
Proposed online date
April 2025

Location

Marker shows the centre of Taylor County; the queue data does not give exact sites.