United States β€Ί Grid β€Ί Interconnection queues β€Ί Iowa

ONSHORE WIND Β· MISO

Onshore wind project J1859, Pottawattamie County

Onshore wind project J1859, Pottawattamie County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Pottawattamie County, Iowa, connecting to MIDAMERICAN ENERGY CO..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2021 (completed)
  2. Withdrawn / abandonedOct 2021 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J1859
Grid region
MISO (Midcontinent)
Utility / transmission owner
MIDAMERICAN ENERGY CO.
Connection point (POI)
Council Bluffs - Fallow Avenue 345kV Line Tap
Location
Pottawattamie County, Iowa
Technology
Wind: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3
Queue status
Withdrawn
Entered queue
16 August 2021
Proposed online date
September 2024
Withdrawn
October 2021

Location

Marker shows the centre of Pottawattamie County; the queue data does not give exact sites.

Power plants in Iowa Β· Transmission lines in Iowa

Other requests in Pottawattamie County