United States โ€บ Grid โ€บ Interconnection queues โ€บ Georgia

OCTARY USA ยท INTERCONNECTION QUEUES

Queue requests in study in Georgia

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown14029.2 GW
Active in queue46.5 GW204 requests
Agreement signed16.6 GW57 requests
Withdrawn510106.6 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

140 requests ยท page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Smarr CC
Gas
2,000 MWIn study Monroe, GASoutheast Aug 2024target 2028
Solar + storage project IC-942, Glynn County
Solar + storage
1,200 MWPaused / redesign Glynn, GASoutheast Mar 2021target 2025
Flint River 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Oct 2024target 2029
Flint River 2 780 MW Unit
Gas
780 MWIn study Mitchell, GASoutheast Mar 2025target 2029
Gas project 25-IC-1330, Hancock County
Gas
759 MWIn study Hancock, GASoutheast Apr 2025target 2030
Gas project 25-IC-1329, Putnam County
Gas
759 MWIn study Putnam, GASoutheast Apr 2025target 2030
Gas project 25-IC-1327, Coweta County
Gas
759 MWIn study Coweta, GASoutheast Apr 2025target 2030
Gas project IC-1260, Effingham County
Gas
722 MWIn study Effingham, GASoutheast Mar 2024target 2031
Battery storage project IC-974, Fulton County
Battery storage
600 MWPaused / redesign Fulton, GASoutheast Jul 2021target 2025
Battery storage project 25-IC-1374, Hancock County
Battery storage
600 MWIn study Hancock, GASoutheast Apr 2025target 2029
Solar project IC-1147, Monroe County
Solar
500 MWPaused / redesign Monroe, GASoutheast Jun 2023target 2030
Battery storage project IC-1170, Douglas County
Battery storage
500 MWPaused / redesign Douglas, GASoutheast Aug 2023target 2030
Battery storage project 25-IC-1311, Mcduffie County
Battery storage
500 MWIn study Mcduffie, GASoutheast Apr 2025target 2028
Pepper Hammock 500 Solar
Solar
500 MWIn study Glynn, GASoutheast Jul 2022target 2024
Solar project IC-1084, Coweta County
Solar
470 MWPaused / redesign Coweta, GASoutheast Oct 2022target 2027
Battery storage project 25-IC-1385, Hancock County
Battery storage
450 MWIn study Hancock, GASoutheast Apr 2025target 2030
Battery storage project 25-IC-1375, Jackson County
Battery storage
325 MWIn study Jackson, GASoutheast Apr 2025target 2031
TOCE GA Solar 4
Solar + storage
325 MWIn study Jefferson, GASoutheast Jan 2024target 2027
Battery storage project IC-1144, Bartow County
Battery storage
260 MWPaused / redesign Bartow, GASoutheast Jun 2023target 2028
Battery storage project 25-IC-1312, Coweta County
Battery storage
250 MWIn study Coweta, GASoutheast Apr 2025target 2028
Solar + storage project IC-932, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Rock House Solar
Solar + storage
250 MWIn study Mcduffie, GASoutheast Jan 2022target 2025
Solar + storage project IC-933, Glynn County
Solar + storage
250 MWPaused / redesign Glynn, GASoutheast Dec 2020target 2024
Battery storage project 25-IC-1313, Bartow County
Battery storage
250 MWIn study Bartow, GASoutheast Apr 2025target 2028
Solar project 25-IC-1326, Jasper County
Solar
250 MWIn study Jasper, GASoutheast Apr 2025target 2030
Talbot U7
Gas
250 MWIn study Talbot, GASoutheast Aug 2024target 2029
Solar project IC-1149, Mitchell County
Solar
250 MWPaused / redesign Mitchell, GASoutheast Jul 2023target 2028
Battery storage project 25-IC-1334, Effingham County
Battery storage
250 MWIn study Effingham, GASoutheast Apr 2025target 2029
Solar project IC-972, Jasper County
Solar
250 MWPaused / redesign Jasper, GASoutheast Jul 2021target 2024
Thundering Springs
Solar + storage
240 MWIn study Laurens, GASoutheast Nov 20192023
Solar project IC-1014, Jeff Davis County
Solar
230 MWPaused / redesign Jeff Davis, GASoutheast Jan 2022target 2025
Solar project IC-1098, Taylor County
Solar
225 MWPaused / redesign Taylor, GASoutheast Nov 2022target 2027
Hammond Solar
Solar
225 MWIn study Floyd, GASoutheast Sep 2023target 2025
Solar project IC-908, Turner County
Solar
220 MWPaused / redesign Turner, GASoutheast Oct 2020target 2023
Pecan Energy Storage
Solar + storage
208 MWIn study Mitchell, GASoutheast Oct 2023target 2029
Washington County Solar
Solar + storage
203 MWIn study Washington, GASoutheast Oct 2024target 2027
Pepper Hammock Solar
Solar
200 MWIn study Glynn, GASoutheast Jun 2022target 2024
Solar project IC-990, Toombs County
Solar
200 MWPaused / redesign Toombs, GASoutheast Oct 2021target 2025
Solar + storage project IC-1013, Oglethorpe County
Solar + storage
200 MWPaused / redesign Oglethorpe, GASoutheast Jan 2022target 2025
Battery storage project IC-1272, Paulding County
Battery storage
200 MWIn study Paulding, GASoutheast Mar 2024target 2030
Fairboro Solar
Solar
200 MWIn study Ware, GASoutheast Dec 2021target 2023
SR Bartown frmly Jefferson
Solar
200 MWIn study Jefferson, GASoutheast Dec 2024target 2029
Live Oak Solar
Solar + storage
200 MWIn study Laurens, GASoutheast May 2023target 2026
Union City Storage I
Battery storage
200 MWIn study Fulton, GASoutheast Dec 20192022
Solar + storage project IC-1042, Rockdale County
Solar + storage
200 MWPaused / redesign Rockdale, GASoutheast Jul 2022target 2026
Pepper Hammock 200 MW
Solar
200 MWIn study Glynn, GASoutheast Aug 2023target 2026
Oakhurst Solar Farm
Solar + storage
200 MWIn study Mitchell, GASoutheast Apr 20172021
Solar + storage project 25-IC-1383, Dougherty County
Solar + storage
199 MWIn study Dougherty, GASoutheast Apr 2025target 2030
Solar project 25-IC-1342, Laurens County
Solar
199 MWIn study Laurens, GASoutheast Apr 2025target 2029
SR Wrens
Solar
194 MWIn study Jefferson, GASoutheast Dec 2024target 2029
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)