United States › Grid › Interconnection queues › Georgia
SOLAR · SOUTHEASTSolar project 25-IC-1342, Laurens County
Solar project 25-IC-1342, Laurens County is a 199 MW solar request in interconnection study in the Southeast interconnection queue, in Laurens County, Georgia, connecting to Southern Company.
Queue statusIn planning
- PlanningQueued Apr 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Feb 2029 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 25-IC-1342
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Eastman Primary - Hatch 230 kV Line
- Location
- Laurens County, Georgia
- Technology
- Solar: 199 MW
- Total requested
- 199 MW
- Service type
- Energy only (ERIS)
- Study phase
- Facility Study
- Queue status
- Active
- Entered queue
- 14 April 2025
- Proposed online date
- February 2029
Location
Marker shows the centre of Laurens County; the queue data does not give exact sites.
Other requests in Laurens County
- Solar project IC-1206, Laurens CountySolar · 225 MW · agreement signed
- Solar + storage project IC-1265, Laurens CountySolar + storage · 200 MW · agreement signed
- Solar project IC-1044, Laurens CountySolar · 150 MW · agreement signed
- Thundering SpringsSolar + storage · 240 MW · in study
- Live Oak SolarSolar + storage · 200 MW · in study
- Battery storage project 25-IC-1343, Laurens CountyBattery storage · 100 MW · in study
- Dublin Biomass -GPSOther · 45.0 MW · built
- Dublin Biomass - SPFTGas · 38.0 MW · built
- Solar project IC-634, Laurens CountySolar · 249 MW · withdrawn
- Solar project IC-727, Laurens CountySolar · 240 MW · withdrawn
- Solar project IC-544, Laurens CountySolar · 240 MW · withdrawn
- Solar project IC-543, Laurens CountySolar · 40.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem