SOLAR Β· SOUTHEAST

Solar project IC-634, Laurens County

Solar project IC-634, Laurens County is a 249 MW solar request withdrawn in the Southeast interconnection queue, in Laurens County, Georgia, connecting to Southern Company.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2017 (completed)
  2. Withdrawn / abandonedDec 2017 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
IC-634
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Southern Company
Connection point (POI)
Eastman Primary - Hatch 230 kV Line
Location
Laurens County, Georgia
Technology
Solar: 249 MW
Total requested
249 MW
Service type
NRIS and ERIS
Study phase
Withdrawn
Queue status
Withdrawn
Entered queue
21 April 2017
Withdrawn
December 2017

Location

Marker shows the centre of Laurens County; the queue data does not give exact sites.

Power plants in Georgia Β· Transmission lines in Georgia

Other requests in Laurens County