Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown131,386 MW
Active in queue1,386 MW13 requests
Agreement signed0.0 MW0 requests
Withdrawn00.0 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

13 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project FC100382, Osceola County
Gas Β· Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Gas project FC100386, Osceola County
Gas Β· Duke Energy Florida, LLC
265 MWIn study Osceola, FLSoutheast Dec 2025target 2030
Battery storage project FC100380, Citrus County
Battery storage Β· Duke Energy Florida, LLC
199 MWIn study Citrus, FLSoutheast Dec 2025target 2030
Gas project 118, Polk County
Gas
132 MWIn study Polk, FLSoutheast Apr 2025target 2026
Battery storage project FC100381, Leon County
Battery storage Β· Duke Energy Florida, LLC
100 MWIn study Leon, FLSoutheast Dec 2025target 2031
Solar project FC100384, Suwannee County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project FC100383, Liberty County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Liberty, FLSoutheast Dec 2025target 2029
Solar project FC100385, Suwannee County
Solar Β· Duke Energy Florida, LLC
74.9 MWIn study Suwannee, FLSoutheast Dec 2025target 2030
Solar project 121, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast May 2025target 2027
Solar project 122, Hillsborough County
Solar
74.5 MWIn study Hillsborough, FLSoutheast May 2025target 2027
Battery storage project 120, Polk County
Battery storage
20.0 MWIn study Polk, FLSoutheast May 2025target 2027
Solar project 123, Polk County
Solar
19.5 MWIn study Polk, FLSoutheast May 2025target 2027
Gas project FC100379, Orange County
Gas Β· Masked
12.0 MWIn study Orange, FLSoutheast Nov 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)