United States β€Ί Grid β€Ί Interconnection queues β€Ί Connecticut

OCTARY USA Β· INTERCONNECTION QUEUES

Withdrawn queue requests in Connecticut (2023 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown294,890 MW
Active in queue5.0 MW1 requests
Agreement signed0.0 MW0 requests
Withdrawn294,890 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

29 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Battery Storage
Battery storage
326 MWWithdrawn / abandoned Hartford, CTISO-NE Jul 2023target 2029
Battery Storage
Battery storage
326 MWWithdrawn / abandoned New Haven, CTISO-NE Mar 2023target 2027
Battery Storage
Battery storage
305 MWWithdrawn / abandoned Middlesex, CTISO-NE Jun 2023target 2026
Battery Storage
Battery storage
300 MWWithdrawn / abandoned New London, CTISO-NE Aug 2023target 2028
Battery Storage
Battery storage
300 MWWithdrawn / abandoned Windham, CTISO-NE Jun 2023target 2028
Battery Storage
Battery storage
289 MWWithdrawn / abandoned New London, CTISO-NE Feb 2023target 2027
Battery Storage
Battery storage
289 MWWithdrawn / abandoned Middlesex, CTISO-NE Feb 2023target 2024
Battery Storage Addition
Battery storage
284 MWWithdrawn / abandoned Middlesex, CTISO-NE May 2023target 2026
Battery Storage
Battery storage
263 MWWithdrawn / abandoned New Haven, CTISO-NE Feb 2023target 2027
Battery Storage
Battery storage
257 MWWithdrawn / abandoned New London, CTISO-NE Aug 2023target 2028
Battery Storage
Battery storage
238 MWWithdrawn / abandoned Hartford, CTISO-NE Dec 2023target 2027
Gas Turbine
Gas
233 MWWithdrawn / abandoned Fairfield, CTISO-NE May 2023target 2026
Battery Storage
Battery storage
201 MWWithdrawn / abandoned Fairfield, CTISO-NE Mar 2023target 2026
Battery Storage
Battery storage
197 MWWithdrawn / abandoned Hartford, CTISO-NE Jan 2023target 2026
Battery Storage
Battery storage
175 MWWithdrawn / abandoned New London, CTISO-NE Jun 2023target 2027
Battery Storage
Battery storage
156 MWWithdrawn / abandoned Fairfield, CTISO-NE Feb 2023target 2027
Battery Storage
Battery storage
136 MWWithdrawn / abandoned New Haven, CTISO-NE Feb 2023target 2027
Battery Storage
Battery storage
135 MWWithdrawn / abandoned New Haven, CTISO-NE Dec 2023target 2027
Battery Storage
Battery storage
103 MWWithdrawn / abandoned New London, CTISO-NE Aug 2023target 2029
Battery Storage
Battery storage
102 MWWithdrawn / abandoned Hartford, CTISO-NE May 2023target 2026
Battery Storage
Battery storage
100 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2023target 2026
Battery Storage
Battery storage
75.0 MWWithdrawn / abandoned New London, CTISO-NE Jan 2023target 2028
Battery Storage
Battery storage
53.7 MWWithdrawn / abandoned New Haven, CTISO-NE May 2023target 2026
Enfield DG Cluster
Solar + storage
18.8 MWWithdrawn / abandoned Hartford, CTISO-NE Jan 2023target 2025
Battery Storage
Battery storage
10.0 MWWithdrawn / abandoned Middlesex, CTISO-NE Feb 2023target 2024
Battery Storage
Battery storage
7.0 MWWithdrawn / abandoned Hartford, CTISO-NE Aug 2023target 2024
Scitico DG Cluster
Solar + storage
5.2 MWWithdrawn / abandoned Hartford, CTISO-NE Jan 2023target 2023
Battery Storage
Battery storage
5.1 MWWithdrawn / abandoned Middlesex, CTISO-NE Jan 2023target 2025
Fuel Cell
Other
1.8 MWWithdrawn / abandoned Hartford, CTISO-NE Feb 2023target 2024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)