United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 197 MW battery storage request withdrawn in the ISO-NE interconnection queue, in Hartford County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2023 (completed)
  2. Withdrawn / abandonedOct 2024 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1346
Grid region
ISO-NE (New England)
Connection point (POI)
Eversource, North Bloomfield Substation, 345kV BUS.
Location
Hartford County, Connecticut
Technology
Battery: 197 MW
Total requested
197 MW
Service type
Network resource (NRIS)
Study phase
Feasibility Study
Queue status
Withdrawn
Entered queue
12 January 2023
Proposed online date
September 2026
Withdrawn
October 2024

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in Hartford County