🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Connecticut

BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 75.0 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New London County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jan 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1345
Grid region
ISO-NE (New England)
Connection point (POI)
Shunock 115kV Substation, Pendleton Hill Substation, North Stonington, CT 06359
Location
New London County, Connecticut
Technology
Battery: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
10 January 2023
Proposed online date
June 2028
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County