BATTERY STORAGE · ISO-NE

Battery Storage

Battery Storage is a 175 MW battery storage request withdrawn in the ISO-NE interconnection queue, in New London County, Connecticut.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2023 (completed)
  2. Withdrawn / abandonedOct 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
1420
Grid region
ISO-NE (New England)
Connection point (POI)
Existing Eversource 115kV structure on Line 1410, West of 39 Dock Road (41.430126, -72.103424).
Location
New London County, Connecticut
Technology
Battery: 175 MW
Total requested
175 MW
Service type
Network resource (NRIS)
Queue status
Withdrawn
Entered queue
29 June 2023
Proposed online date
December 2027
Withdrawn
October 2025

Location

No county location in the queue data.

Power plants in Connecticut · Transmission lines in Connecticut

Other requests in New London County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem