United States โบ Grid โบ Interconnection queues โบ California
OCTARY USA ยท INTERCONNECTION QUEUESWithdrawn queue requests in California (2012 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Alamitos Energy Center Gas |
1,903 MW | Withdrawn / abandoned |
| Huntington Beach Gas |
939 MW | Withdrawn / abandoned |
| Gas project Q31, San Bernardino County Gas |
850 MW | Withdrawn / abandoned |
| Golden Hills Power Gas |
550 MW | Withdrawn / abandoned |
| Solar project Q27, San Bernardino County Solar |
515 MW | Withdrawn / abandoned |
| Blythe Mesa Solar II - C5 Solar |
500 MW | Withdrawn / abandoned |
| Redondo Beach Energy Project Gas |
476 MW | Withdrawn / abandoned |
| Solar project Q38, Kern County Solar |
470 MW | Withdrawn / abandoned |
| Vista Power Project Gas |
402 MW | Withdrawn / abandoned |
| Solar project Q39, Kern County Solar |
396 MW | Withdrawn / abandoned |
| Desert Butte Solar Farm Solar |
387 MW | Withdrawn / abandoned |
| Prospect Energy Center Gas |
310 MW | Withdrawn / abandoned |
| Tenaska Mountain Basin Gas |
300 MW | Withdrawn / abandoned |
| Solar project Q36, San Bernardino County Solar |
300 MW | Withdrawn / abandoned |
| Highwind Power Project Gas |
291 MW | Withdrawn / abandoned |
| Stage Coach Solar Solar + storage |
250 MW | Withdrawn / abandoned |
| Mirage Solar Solar |
250 MW | Withdrawn / abandoned |
| Solar project Q34, Inyo County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project Q41, San Bernardino County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project Q32, San Bernardino County Solar |
200 MW | Withdrawn / abandoned |
| Firebaugh Solar - C5 Solar |
200 MW | Withdrawn / abandoned |
| Delta Solano Wind Onshore wind |
175 MW | Withdrawn / abandoned |
| Mule Mountain - C5 Solar |
150 MW | Withdrawn / abandoned |
| Solar project Q28, San Bernardino County Solar |
150 MW | Withdrawn / abandoned |
| Quartz 1 Solar Solar |
150 MW | Withdrawn / abandoned |
| Quartz 2 Solar Solar |
150 MW | Withdrawn / abandoned |
| Red Mountain Wind Energy Center - C5 Onshore wind |
150 MW | Withdrawn / abandoned |
| Sanborn Solar Solar |
150 MW | Withdrawn / abandoned |
| Solar + storage project Q25, Kern County Solar + storage |
150 MW | Withdrawn / abandoned |
| Solar project Q26, Kern County Solar |
150 MW | Withdrawn / abandoned |
| Siberia Phase III Segs Solar |
140 MW | Withdrawn / abandoned |
| Great Valley Solar 2 Solar |
120 MW | Withdrawn / abandoned |
| Lucerne Valley 100 MW PV Plant Solar |
100 MW | Withdrawn / abandoned |
| Lucerne Solar Energy - C5 Solar |
100 MW | Withdrawn / abandoned |
| Dunnigan Hills Onshore wind |
100 MW | Withdrawn / abandoned |
| Los Robles Solar |
100 MW | Withdrawn / abandoned |
| Belridge Solar Energy 2 Project Solar |
80.0 MW | Withdrawn / abandoned |
| Newhall Solar Energy Project Solar |
80.0 MW | Withdrawn / abandoned |
| Yuha Basin Solar Solar |
75.0 MW | Withdrawn / abandoned |
| Yermo Solar Solar |
75.0 MW | Withdrawn / abandoned |
| Horse Lake Onshore wind |
51.0 MW | Withdrawn / abandoned |
| Backus Solar Energy Solar |
50.0 MW | Withdrawn / abandoned |
| Wellhead Power Nella CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Wellhead Power Lemietta CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Wellhead Power Woodland CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Wellhead Power Midfruit CHP Gas |
49.0 MW | Withdrawn / abandoned |
| Tehachapi Valley Solar I Solar |
45.0 MW | Withdrawn / abandoned |
| KPP - 45 Gas |
45.0 MW | Withdrawn / abandoned |
| SPS As 40MW PV Generation Facility Solar |
40.0 MW | Withdrawn / abandoned |
| Honey Lake Geothermal Project Geothermal |
20.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)