🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › California

GEOTHERMAL · CAISO

Honey Lake Geothermal Project

Honey Lake Geothermal Project is a 20.0 MW geothermal request withdrawn in the CAISO interconnection queue, in Lassen County, California, connecting to PGAE.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Apr 2012 (completed)
  2. Withdrawn / abandonedMay 2013 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
910
Grid region
CAISO (California)
Utility / transmission owner
PGAE
Connection point (POI)
Honey Lake Substation 60 kV
Location
Lassen County, California
Technology
Geothermal: 20.0 MW
Total requested
20.0 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Withdrawn
Entered queue
2 April 2012
Proposed online date
June 2016
Withdrawn
May 2013

Location

Marker shows the centre of Lassen County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Lassen County