United States β€Ί Grid β€Ί Interconnection queues β€Ί California

SOLAR Β· WEST

Solar project Q38, Kern County

Solar project Q38, Kern County is a 470 MW solar request withdrawn in the West interconnection queue, in Kern County, California, connecting to Los Angeles Department of Water and Power.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2012 (completed)
  2. Withdrawn / abandonedOct 2014 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
Q38
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Barren Ridge 230 kV Sw Station
Location
Kern County, California
Technology
Solar: 470 MW
Total requested
470 MW
Queue status
Withdrawn
Entered queue
29 November 2012
Proposed online date
November 2014
Withdrawn
October 2014

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California Β· Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem