Solar interconnection queue in Alabama

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown394,656 MW
Active in queue4,656 MW39 requests
Agreement signed1,527 MW9 requests
Withdrawn22021.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

39 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project IC-1071, Perry County
Solar
336 MWAgreement signed Perry, ALSoutheast Sep 2022target 2027
Solar project IC-1266, Bullock County
Solar
200 MWAgreement signed Bullock, ALSoutheast Mar 2024target 2027
Solar project 385, Lawrence County
Solar
200 MWAgreement signed Lawrence, ALSoutheast Aug 2019target 2026
Solar project 25-IC-1368, Mobile County
Solar
200 MWIn study Mobile, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1376, Baldwin County
Solar
199 MWIn study Baldwin, ALSoutheast Apr 2025target 2028
Solar project 25-IC-1347, Escambia County
Solar
199 MWIn study Escambia, ALSoutheast Apr 2025target 2028
Solar project 25-IC-1365, Greene County
Solar
195 MWIn study Greene, ALSoutheast Apr 2025target 2029
Solar project 405, Lawrence County
Solar
193 MWAgreement signed Lawrence, ALSoutheast Nov 2019target 2027
Solar project IC-1225, Baldwin County
Solar
180 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Solar project 387, Colbert County
Solar
178 MWAgreement signed Colbert, ALSoutheast Aug 2019target 2027
Solar project 25-IC-1361, Cherokee County
Solar
170 MWIn study Cherokee, ALSoutheast Apr 2025target 2029
Solar project IC-1251, Lee County
Solar
157 MWPaused / redesign Lee, ALSoutheast Mar 2024target 2028
Solar project 25-IC-1366, Dale County
Solar
110 MWIn study Dale, ALSoutheast Apr 2025target 2029
Solar project 662, Madison County
Solar
110 MWIn study Madison, ALSoutheast Oct 2024target 2027
Solar project IC-1043, Coosa County
Solar
100 MWPaused / redesign Coosa, ALSoutheast Jul 2022target 2030
Solar project IC-1162, Talladega County
Solar
100 MWPaused / redesign Talladega, ALSoutheast Aug 2023target 2027
Solar project 660, Jackson County
Solar
99.0 MWIn study Jackson, ALSoutheast Oct 2024target 2032
Solar project 25-IC-1336, Clarke County
Solar
93.0 MWIn study Clarke, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1354, Dale County
Solar
91.0 MWIn study Dale, ALSoutheast Apr 2025target 2029
Solar project IC-1066, Dale County
Solar
80.0 MWPaused / redesign Dale, ALSoutheast Sep 2022target 2030
Solar project IC-832, Monroe County
Solar
80.0 MWPaused / redesign Monroe, ALSoutheast Oct 2019target 2026
Solar project IC-831, Washington County
Solar
80.0 MWPaused / redesign Washington, ALSoutheast Oct 2019target 2026
Solar project IC-1051, Escambia County
Solar
80.0 MWPaused / redesign Escambia, ALSoutheast Aug 2022target 2027
Solar project IC-1083, Marengo County
Solar
80.0 MWPaused / redesign Marengo, ALSoutheast Oct 2022target 2026
Solar project IC-1039, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast May 2022target 2026
Solar project IC-1132, Hale County
Solar
80.0 MWPaused / redesign Hale, ALSoutheast Mar 2023target 2027
Solar project IC-1224, Baldwin County
Solar
80.0 MWAgreement signed Baldwin, ALSoutheast Jan 2024target 2028
Solar project IC-1036, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast May 2022target 2027
Solar project IC-943, Talladega County
Solar
80.0 MWPaused / redesign Talladega, ALSoutheast Mar 2021target 2025
Solar project IC-926, Montgomery County
Solar
80.0 MWPaused / redesign Montgomery, ALSoutheast Dec 2020target 2027
Solar project IC-1075, Dallas County
Solar
80.0 MWPaused / redesign Dallas, ALSoutheast Oct 2022target 2027
Solar project IC-975, Dale County
Solar
80.0 MWPaused / redesign Dale, ALSoutheast Jul 2021target 2025
Solar project IC-1128, Perry County
Solar
79.9 MWAgreement signed Perry, ALSoutheast Mar 2023target 2027
Solar project IC-1121, Montgomery County
Solar
79.9 MWPaused / redesign Montgomery, ALSoutheast Mar 2023target 2027
Solar project IC-1127, Perry County
Solar
79.9 MWAgreement signed Perry, ALSoutheast Mar 2023target 2027
Solar project IC-1122, Montgomery County
Solar
79.9 MWPaused / redesign Montgomery, ALSoutheast Mar 2023target 2027
Solar project 25-IC-1360, Sumter County
Solar
75.0 MWIn study Sumter, ALSoutheast Apr 2025target 2029
Solar project 25-IC-1357, Monroe County
Solar
71.0 MWIn study Monroe, ALSoutheast Apr 2025target 2029
Solar project IC-1214, Houston County
Solar
40.0 MWPaused / redesign Houston, ALSoutheast Dec 2023target 2027

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)