United States › Grid › Interconnection queues › Alabama
SOLAR · SOUTHEASTSolar project IC-832, Monroe County
Solar project IC-832, Monroe County is a 80.0 MW solar request suspended in the Southeast interconnection queue, in Monroe County, Alabama, connecting to Southern Company.
Queue statusPaused / redesign
- PlanningQueued Oct 2019 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2026 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- IC-832
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Southern Company
- Connection point (POI)
- Barry - Monroeville 115 kV Line
- Location
- Monroe County, Alabama
- Technology
- Solar: 80.0 MW
- Total requested
- 80.0 MW
- Service type
- Network resource (NRIS)
- Queue status
- Suspended
- Entered queue
- 17 October 2019
- Proposed online date
- June 2026
Location
Marker shows the centre of Monroe County; the queue data does not give exact sites.
Other requests in Monroe County
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem