Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown13610.7 GW
Active in queue1,358 MW6 requests
Agreement signed263 MW3 requests
Withdrawn13610.7 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

136 requests Β· page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Other project Q218, San Juan County
Other
1,200 MWWithdrawn / abandoned San Juan, NMWest Mar 2013target 2020
Other project 2013-G4
Other
750 MWWithdrawn / abandoned West Jul 2013target 2022
Other project Q219, Maricopa County
Other
634 MWWithdrawn / abandoned Maricopa, AZWest Sep 2013target 2018
Solar + storage project Q45, Clark County
Solar + storage
600 MWWithdrawn / abandoned Clark, NVWest Dec 2013target 2014
Hydro project 509, Klamath County
Hydro Β· CBG Portland, LLC
600 MWWithdrawn / abandoned Klamath, ORWest Aug 2013target 2019
Gas project 510, Coos County
Gas Β· Entiv Organic, LLC
336 MWWithdrawn / abandoned Coos, ORWest Aug 2013target 2017
Onshore wind project 164, Rosebud County
Onshore wind
301 MWWithdrawn / abandoned Rosebud, MTWest Sep 2013target 2021
Onshore wind project 163, Rosebud County
Onshore wind
301 MWWithdrawn / abandoned Rosebud, MTWest Jul 2013target 2016
Solar project Q43, Kern County
Solar
300 MWWithdrawn / abandoned Kern, CAWest Jun 2013target 2016
Gas project 498, Sweetwater County
Gas
300 MWWithdrawn / abandoned Sweetwater, WYWest Jun 2013target 2016
Solar project Q06, Maricopa County
Solar
300 MWWithdrawn / abandoned Maricopa, AZWest Aug 2013target 2021
Onshore wind project GI-1306, Bon Homme County
Onshore wind
250 MWWithdrawn / abandoned Bon Homme, SDWest Jun 2013target 2015
Onshore wind project GI-1305, Williams County
Onshore wind
250 MWWithdrawn / abandoned Williams, NDWest May 2013target 2014
Onshore wind project GI-1310, Grant County
Onshore wind
201 MWWithdrawn / abandoned Grant, SDWest Nov 2013target 2017
Onshore wind project GI-1311, Billings County
Onshore wind
201 MWWithdrawn / abandoned Billings, NDWest Nov 2013target 2017
Onshore wind project GI-1312, Stark County
Onshore wind
201 MWWithdrawn / abandoned Stark, NDWest Nov 2013target 2017
Onshore wind project GI-2013-2, Lincoln County
Onshore wind
200 MWWithdrawn / abandoned Lincoln, COWest Mar 2013target 2016
Onshore wind project GI-2013-6, Logan County
Onshore wind
200 MWWithdrawn / abandoned Logan, COWest Sep 2013target 2016
Onshore wind project GI-2013-1, Pueblo County
Onshore wind
200 MWWithdrawn / abandoned Pueblo, COWest Feb 2013target 2015
Solar project Company 125, Clark County
Solar
200 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Onshore wind project IA-PNM-2013-02, Roosevelt County
Onshore wind
198 MWWithdrawn / abandoned Roosevelt, NMWest May 2013target 2014
Onshore wind project 460, Millard County
Onshore wind
160 MWWithdrawn / abandoned Millard, UTWest Jan 2013
Solar project Company 123, Clark County
Solar
150 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Onshore wind project GI-2013-7, Logan County
Onshore wind
140 MWWithdrawn / abandoned Logan, COWest Sep 2013target 2014
Onshore wind project GI-1308, Ward County
Onshore wind
120 MWWithdrawn / abandoned Ward, NDWest Jul 2013target 2015
Onshore wind project GI-1302, Roosevelt County
Onshore wind
120 MWWithdrawn / abandoned Roosevelt, MTWest Mar 2013target 2016
Solar project Company 120, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2023
Solar project Company 124, Clark County
Solar
100 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Gas project GI-1304, Mckenzie County
Gas
100 MWWithdrawn / abandoned Mckenzie, NDWest Apr 2013target 2016
Onshore wind project GI-1301, Grant County
Onshore wind Β· Summit Wind Farm
90.0 MWWithdrawn / abandoned Grant, SDWest Mar 2013target 2018
Solar project 541, San Juan County
Solar
80.0 MWWithdrawn / abandoned San Juan, UTWest Dec 2013target 2015
Onshore wind project 474, Washington County
Onshore wind
80.0 MWWithdrawn / abandoned Washington, UTWest Mar 2013target 2014
Onshore wind project 470, Tooele County
Onshore wind
78.2 MWWithdrawn / abandoned Tooele, UTWest Feb 2013target 2014
Hydro project G0496, Pend Oreille County
Hydro
70.0 MWWithdrawn / abandoned Pend Oreille, WAWest Dec 2013target 2014
Onshore wind project 540, San Juan County
Onshore wind
70.0 MWWithdrawn / abandoned San Juan, UTWest Dec 2013target 2015
Gas project G0495, Clark County
Gas
60.0 MWWithdrawn / abandoned Clark, WAWest Dec 2013target 2016
Solar project Company 121, Clark County
Solar
58.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Solar project Company 126, Clark County
Solar
58.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Solar project 461, Iron County
Solar
51.0 MWWithdrawn / abandoned Iron, UTWest Jan 2013target 2014
Solar project Company 118, Clark County
Solar
51.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2015
Solar project 505, Iron County
Solar
50.4 MWWithdrawn / abandoned Iron, UTWest Jul 2013target 2015
Solar project 507, Iron County
Solar
50.4 MWWithdrawn / abandoned Iron, UTWest Aug 2013target 2015
Solar project 465, San Juan County
Solar
50.4 MWWithdrawn / abandoned San Juan, UTWest Feb 2013target 2015
Solar project Company 122, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2016
Solar project Q27, Pinal County
Solar
50.0 MWWithdrawn / abandoned Pinal, AZWest Jul 2013target 2016
Solar project Company 128, Clark County
Solar
50.0 MWWithdrawn / abandoned Clark, NVWest Sep 2013target 2025
Solar project Q28, Pinal County
Solar
50.0 MWWithdrawn / abandoned Pinal, AZWest Nov 2013target 2017
Gas project 508, Utah County
Gas Β· Jordan Cove Energy Project, L.P.
45.0 MWWithdrawn / abandoned Utah, UTWest Aug 2013target 2014
Solar project 525, Iron County
Solar
40.0 MWWithdrawn / abandoned Iron, UTWest Oct 2013target 2016
Solar project 468, Duchesne County
Solar
40.0 MWWithdrawn / abandoned Duchesne, UTWest Feb 2013target 2015
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)