United States βΊ Grid βΊ Interconnection queues
OCTARY USA Β· INTERCONNECTION QUEUESWithdrawn queue requests in West (non-ISO utilities) (2013 requests)
Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.
Map
Requests
| Project | Capacity | Status |
|---|---|---|
| Other project Q218, San Juan County Other |
1,200 MW | Withdrawn / abandoned |
| Other project 2013-G4 Other |
750 MW | Withdrawn / abandoned |
| Other project Q219, Maricopa County Other |
634 MW | Withdrawn / abandoned |
| Solar + storage project Q45, Clark County Solar + storage |
600 MW | Withdrawn / abandoned |
| Hydro project 509, Klamath County Hydro Β· CBG Portland, LLC |
600 MW | Withdrawn / abandoned |
| Gas project 510, Coos County Gas Β· Entiv Organic, LLC |
336 MW | Withdrawn / abandoned |
| Onshore wind project 164, Rosebud County Onshore wind |
301 MW | Withdrawn / abandoned |
| Onshore wind project 163, Rosebud County Onshore wind |
301 MW | Withdrawn / abandoned |
| Solar project Q43, Kern County Solar |
300 MW | Withdrawn / abandoned |
| Gas project 498, Sweetwater County Gas |
300 MW | Withdrawn / abandoned |
| Solar project Q06, Maricopa County Solar |
300 MW | Withdrawn / abandoned |
| Onshore wind project GI-1306, Bon Homme County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project GI-1305, Williams County Onshore wind |
250 MW | Withdrawn / abandoned |
| Onshore wind project GI-1310, Grant County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project GI-1311, Billings County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project GI-1312, Stark County Onshore wind |
201 MW | Withdrawn / abandoned |
| Onshore wind project GI-2013-2, Lincoln County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-2013-6, Logan County Onshore wind |
200 MW | Withdrawn / abandoned |
| Onshore wind project GI-2013-1, Pueblo County Onshore wind |
200 MW | Withdrawn / abandoned |
| Solar project Company 125, Clark County Solar |
200 MW | Withdrawn / abandoned |
| Onshore wind project IA-PNM-2013-02, Roosevelt County Onshore wind |
198 MW | Withdrawn / abandoned |
| Onshore wind project 460, Millard County Onshore wind |
160 MW | Withdrawn / abandoned |
| Solar project Company 123, Clark County Solar |
150 MW | Withdrawn / abandoned |
| Onshore wind project GI-2013-7, Logan County Onshore wind |
140 MW | Withdrawn / abandoned |
| Onshore wind project GI-1308, Ward County Onshore wind |
120 MW | Withdrawn / abandoned |
| Onshore wind project GI-1302, Roosevelt County Onshore wind |
120 MW | Withdrawn / abandoned |
| Solar project Company 120, Clark County Solar |
100 MW | Withdrawn / abandoned |
| Solar project Company 124, Clark County Solar |
100 MW | Withdrawn / abandoned |
| Gas project GI-1304, Mckenzie County Gas |
100 MW | Withdrawn / abandoned |
| Onshore wind project GI-1301, Grant County Onshore wind Β· Summit Wind Farm |
90.0 MW | Withdrawn / abandoned |
| Solar project 541, San Juan County Solar |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 474, Washington County Onshore wind |
80.0 MW | Withdrawn / abandoned |
| Onshore wind project 470, Tooele County Onshore wind |
78.2 MW | Withdrawn / abandoned |
| Hydro project G0496, Pend Oreille County Hydro |
70.0 MW | Withdrawn / abandoned |
| Onshore wind project 540, San Juan County Onshore wind |
70.0 MW | Withdrawn / abandoned |
| Gas project G0495, Clark County Gas |
60.0 MW | Withdrawn / abandoned |
| Solar project Company 121, Clark County Solar |
58.0 MW | Withdrawn / abandoned |
| Solar project Company 126, Clark County Solar |
58.0 MW | Withdrawn / abandoned |
| Solar project 461, Iron County Solar |
51.0 MW | Withdrawn / abandoned |
| Solar project Company 118, Clark County Solar |
51.0 MW | Withdrawn / abandoned |
| Solar project 505, Iron County Solar |
50.4 MW | Withdrawn / abandoned |
| Solar project 507, Iron County Solar |
50.4 MW | Withdrawn / abandoned |
| Solar project 465, San Juan County Solar |
50.4 MW | Withdrawn / abandoned |
| Solar project Company 122, Clark County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q27, Pinal County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Company 128, Clark County Solar |
50.0 MW | Withdrawn / abandoned |
| Solar project Q28, Pinal County Solar |
50.0 MW | Withdrawn / abandoned |
| Gas project 508, Utah County Gas Β· Jordan Cove Energy Project, L.P. |
45.0 MW | Withdrawn / abandoned |
| Solar project 525, Iron County Solar |
40.0 MW | Withdrawn / abandoned |
| Solar project 468, Duchesne County Solar |
40.0 MW | Withdrawn / abandoned |
Capacity in the queue by state
Click a state to drill down.
By grid region
ISO/RTO markets and the non-ISO West and Southeast.
- West (non-ISO utilities)136 Β· 10.7 GW
- PJM (Mid-Atlantic, Midwest)80 Β· 10.3 GW
- ERCOT (Texas)52 Β· 8,996 MW
- MISO (Midcontinent)42 Β· 7,775 MW
- CAISO (California)47 Β· 7,426 MW
- SPP (Southwest Power Pool)30 Β· 4,501 MW
- Southeast (non-ISO utilities)62 Β· 4,349 MW
- NYISO (New York)4 Β· 953 MW
- ISO-NE (New England)9 Β· 840 MW
Requests by year joined
Capacity of requests in this view, by the year they entered the queue. Click a year.
Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)