United States β€Ί Grid β€Ί Interconnection queues β€Ί Utah

ONSHORE WIND Β· WEST

Onshore wind project 540, San Juan County

Onshore wind project 540, San Juan County is a 70.0 MW onshore wind request withdrawn in the West interconnection queue, in San Juan County, Utah, connecting to PacifiCorp.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Dec 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
540
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Connection point (POI)
Pinto substation
Location
San Juan County, Utah
Technology
Wind: 70.0 MW
Total requested
70.0 MW
Service type
Network resource (NRIS)
Study phase
WITHDRAWN BY CUSTOMER
Queue status
Withdrawn
Entered queue
23 December 2013
Proposed online date
December 2015

Location

Marker shows the centre of San Juan County; the queue data does not give exact sites.

Power plants in Utah Β· Transmission lines in Utah

Other requests in San Juan County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem