ONSHORE WIND Β· WEST

Onshore wind project 163, Rosebud County

Onshore wind project 163, Rosebud County is a 301 MW onshore wind request withdrawn in the West interconnection queue, in Rosebud County, Montana, connecting to NorthWestern Energy.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jul 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
163
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
500kV at Colstrip Substation
Location
Rosebud County, Montana
Technology
Wind: 301 MW
Total requested
301 MW
Service type
NRIS and ERIS
Queue status
Withdrawn
Entered queue
23 July 2013
Proposed online date
December 2016

Location

Marker shows the centre of Rosebud County; the queue data does not give exact sites.

Power plants in Montana Β· Transmission lines in Montana

Other requests in Rosebud County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem