πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues β€Ί North Dakota

ONSHORE WIND Β· WEST

Onshore wind project GI-1311, Billings County

Onshore wind project GI-1311, Billings County is a 201 MW onshore wind request withdrawn in the West interconnection queue, in Billings County, North Dakota, connecting to WAPA/BEPC/HCPD Integrated System.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2013 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
GI-1311
Grid region
West (non-ISO utilities)
Utility / transmission owner
WAPA/BEPC/HCPD Integrated System
Connection point (POI)
CC-Belfield 345kV
Location
Billings County, North Dakota
Technology
Wind: 201 MW
Total requested
201 MW
Service type
NRIS and ERIS
Study phase
IP
Queue status
Withdrawn
Entered queue
18 November 2013
Proposed online date
December 2017

Location

Marker shows the centre of Billings County; the queue data does not give exact sites.

Power plants in North Dakota Β· Transmission lines in North Dakota

Other requests in Billings County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem