United States βΊ Grid βΊ Interconnection queues βΊ Utah
ONSHORE WIND Β· WESTOnshore wind project 460, Millard County
Onshore wind project 460, Millard County is a 160 MW onshore wind request withdrawn in the West interconnection queue, in Millard County, Utah, connecting to PacifiCorp.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2013 (completed)
- Withdrawn / abandoned (project stopped here)
- ConsentedMar 2014 (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 460
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Connection point (POI)
- Black Rock - Osceola line
- Location
- Millard County, Utah
- Technology
- Wind: 160 MW
- Total requested
- 160 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA signed 3/31/14, Terminated by customer 8/9/16
- Queue status
- Withdrawn
- Entered queue
- 18 January 2013
- Agreement signed
- 31 March 2014
Location
Marker shows the centre of Millard County; the queue data does not give exact sites.
Other requests in Millard County
- Solar + storage project Q105, Millard CountySolar + storage Β· 1,200 MW Β· in study
- Solar + storage project Q93, Millard CountySolar + storage Β· 1,000 MW Β· in study
- Solar + storage project Q51, Millard CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project Q90, Millard CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project Q104, Millard CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project Q50, Millard CountySolar + storage Β· 800 MW Β· in study
- Solar + storage project Q94, Millard CountySolar + storage Β· 700 MW Β· in study
- Solar + storage project Q49, Millard CountySolar + storage Β· 600 MW Β· in study
- Solar + storage project Q53, Millard CountySolar + storage Β· 570 MW Β· in study
- Solar + storage project Q52, Millard CountySolar + storage Β· 518 MW Β· in study
- Solar + storage project C3-036, Millard CountySolar + storage Β· 500 MW Β· in study
- Solar + storage project Q44, Millard CountySolar + storage Β· 450 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem