United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Completed queue projects in West (non-ISO utilities) (2015 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown615,125 MW
Active in queue3,582 MW21 requests
Agreement signed149 MW2 requests
Withdrawn1976,025 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

61 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project 234, Rosebud County
Onshore wind
750 MWOperating Rosebud, MTWest Dec 20152022
Onshore wind project 712, Converse County
Onshore wind Β· Cedar Springs Transmission LLC
520 MWOperating Converse, WYWest Oct 2015target 2020
Solar + storage project Q227, Yuma County
Solar + storage
500 MWOperating Yuma, AZWest Aug 2015target 2021
Solar + storage project Q48, Kern County
Solar + storage
350 MWOperating Kern, CAWest Jul 20152023
Solar + storage project Q47, Kern County
Solar + storage
350 MWOperating Kern, CAWest Jul 20152024
Onshore wind project 713, Converse County
Onshore wind Β· Cedar Springs Transmission LLC
350 MWOperating Converse, WYWest Oct 2015target 2025
Solar project Company 144, Clark County
Solar
300 MWOperating Clark, NVWest Mar 2015target 2018
Onshore wind project 706, Carbon County
Onshore wind Β· PacifiCorp
250 MWOperating Carbon, WYWest Sep 2015target 2020
Onshore wind project 707, Carbon County
Onshore wind Β· PacifiCorp
250 MWOperating Carbon, WYWest Sep 2015target 2020
Onshore wind project 708, Carbon County
Onshore wind Β· PacifiCorp
250 MWOperating Carbon, WYWest Sep 2015target 2020
Solar + storage project Company GU, Washoe County
Solar + storage
200 MWOperating Washoe, NVWest Sep 2015target 2021
Solar project Company GV, Lander County
Solar
101 MWOperating Lander, NVWest Sep 2015target 2016
Solar project 720, Sweetwater County
Solar Β· Sweetwater Solar, LLC
80.0 MWOperating Sweetwater, WYWest Nov 2015target 2018
Boundary Powerhouse
Hydro
70.0 MWOperating Pend Oreille, WAWest Feb 2015target 2016
NMRD Data Center II
Solar
60.0 MWOperating Torrance, NMWest Aug 2015
Solar project Company GR, Washoe County
Solar
60.0 MWOperating Washoe, NVWest Mar 2015target 2016
NMRD Data Center III
Solar
60.0 MWOperating Sandoval Cty, NMWest Aug 2015target 2020
Onshore wind project BHCT G18, Huerfano County
Onshore wind Β· Invenergy (Peak View)
60.0 MWOperating Huerfano, COWest Jan 2015target 2016
Solar project 641, Washington County
Solar Β· Cove Mountain Solar, LLC
58.0 MWOperating Washington, UTWest Feb 2015target 2020
Solar project 721, Klamath County
Solar Β· Skysol, LLC
55.0 MWOperating Klamath, ORWest Nov 2015target 2022
Solar project Q228, Pinal County
Solar
44.3 MWOperating Pinal, AZWest Sep 2015target 2016
Onshore wind project 650, Umatilla County
Onshore wind Β· Oregon Wind Farms, LLC
40.0 MWOperating Umatilla, ORWest Apr 2015target 2020
Smith Creek
Hydro
39.0 MWOperating Boundary, IDWest Jul 2015target 1987
Solar project TI-15-0612, Las Animas County
Solar
30.0 MWOperating Las Animas, COWest Jun 20152016
Solar project TI-15-0227, Luna County
Solar
25.0 MWOperating Luna, NMWest Feb 20152016
Solar project Company GK, Churchill County
Solar
20.0 MWOperating Churchill, NVWest Mar 2015target 2018
Solar project 684, Millard County
Solar Β· Pavant Solar III, LLC
20.0 MWOperating Millard, UTWest Jul 2015target 2016
Onshore wind project 208, Aurora County
Onshore wind
20.0 MWOperating Aurora, SDWest Jul 20152016
Solar project 503, Twin Falls County
Solar Β· Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Aug 20152022
Solar project 502, Twin Falls County
Solar Β· Jackpot Holdings, LLC
20.0 MWOperating Twin Falls, IDWest Aug 20152022
Onshore wind project 205, Brule County
Onshore wind
20.0 MWOperating Brule, SDWest Jul 20152016
Geothermal project Company GX, Lander County
Geothermal
20.0 MWOperating Lander, NVWest Sep 2015target 2016
Hydro project 177, Lake County
Hydro
14.0 MWOperating Lake, MTWest Jan 20152015
Solar project 671, Klamath County
Solar Β· OR Solar 8, LLC
10.0 MWOperating Klamath, ORWest May 2015target 2017
Solar project SGI-PNM-2015-03, San Miguel County
Solar
10.0 MWOperating San Miguel, NMWest Jun 2015
Solar project SGI-PNM-2015-04, Bernalillo County
Solar
10.0 MWOperating Bernalillo, NMWest Jun 2015
Solar project 660, Jackson County
Solar Β· OR Solar 2, LLC
10.0 MWOperating Jackson, ORWest Apr 2015target 2020
Solar project 661, Klamath County
Solar Β· OR Solar 3, LLC
10.0 MWOperating Klamath, ORWest Apr 2015target 2017
Solar project 672, Lake County
Solar Β· OR Solar 6, LLC
10.0 MWOperating Lake, ORWest May 2015target 2017
Solar project 670, Klamath County
Solar Β· OR Solar 5, LLC
8.0 MWOperating Klamath, ORWest May 2015target 2017
Geothermal project Company GW, Mineral County
Geothermal
6.0 MWOperating Mineral, NVWest Sep 2015target 2016
Hydro project 643, Hood County
Hydro Β· Farmers Irrigation District
5.3 MWOperating Hood, ORWest Feb 2015target 2015
Other project 501, Cassia County
Other Β· CAFCo Idaho Refuse Management LLC
5.0 MWOperating Cassia, IDWest Jul 2015target 2018
Horn Rapids Solar Project
Solar + storage
4.0 MWOperating Benton, WAWest Nov 2015target 2017
Gas project 657, Salt Lake County
Gas Β· VA Salt Lake City Health Care System
3.7 MWOperating Salt Lake, UTWest Apr 2015target 2016
Solar project 211, Cascade County
Solar
3.0 MWOperating Cascade, MTWest Sep 20152016
Solar project 193, Big Horn County
Solar
3.0 MWOperating Big Horn, MTWest Feb 20152016
Solar project 179, Lewis And Clark County
Solar
3.0 MWOperating Lewis And Clark, MTWest Jan 20152015
Solar project 204, Lewis And Clark County
Solar
3.0 MWOperating Lewis And Clark, MTWest May 20152016
Solar project 178, Golden Valley County
Solar
3.0 MWOperating Golden Valley, MTWest Jan 20152016
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)