Solar + storage project Q47, Kern County

Solar + storage project Q47, Kern County is a 350 MW solar + storage request built and operating in the West interconnection queue, in Kern County, California, connecting to Los Angeles Department of Water and Power.

Queue statusOperating
  1. PlanningQueued Jul 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingNov 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Q47
Grid region
West (non-ISO utilities)
Utility / transmission owner
Los Angeles Department of Water and Power
Connection point (POI)
Barren Ridge 230 kV Sw Station
Location
Kern County, California
Technology
Solar: 200 MW · Battery: 150 MW
Total requested
350 MW
Study phase
IA Executed
Queue status
Operational
Entered queue
30 July 2015
Proposed online date
November 2022
Came online
November 2024

Location

Marker shows the centre of Kern County; the queue data does not give exact sites.

Power plants in California · Transmission lines in California

Other requests in Kern County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem