GEOTHERMAL · WEST

Geothermal project Company GW, Mineral County

Geothermal project Company GW, Mineral County is a 6.0 MW geothermal request built and operating in the West interconnection queue, in Mineral County, Nevada, connecting to NV Energy.

Queue statusOperating
  1. PlanningQueued Sep 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Feb 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Company GW
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Mineral County, Nevada
Technology
Geothermal: 6.0 MW
Total requested
6.0 MW
Service type
NRIS and ERIS
Study phase
IA Executed
Queue status
Operational
Entered queue
29 September 2015
Proposed online date
February 2016

Location

Marker shows the centre of Mineral County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Mineral County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem