United States › Grid › Interconnection queues › Nevada
GEOTHERMAL · CAISOGreen Borders Geothermal
Green Borders Geothermal is a 62.0 MW geothermal request withdrawn in the CAISO interconnection queue, in Mineral County, Nevada, connecting to SCE.
Queue statusWithdrawn / abandoned
- PlanningQueued Feb 2005 (completed)
- Withdrawn / abandonedOct 2013 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 58
- Grid region
- CAISO (California)
- Utility / transmission owner
- SCE
- Connection point (POI)
- Control 115kV Substation
- Location
- Mineral County, Nevada
- Technology
- Geothermal: 62.0 MW
- Total requested
- 62.0 MW
- Study phase
- Executed
- Queue status
- Withdrawn
- Entered queue
- 22 February 2005
- Proposed online date
- February 2012
- Withdrawn
- October 2013
Location
Marker shows the centre of Mineral County; the queue data does not give exact sites.
Other requests in Mineral County
- Solar + storage project Company LU, Mineral CountySolar + storage · 700 MW · agreement signed
- Geothermal project 25-00391, Mineral CountyGeothermal · 38.5 MW · in study
- Solar + storage project Company LW, Mineral CountySolar + storage · 550 MW · suspended
- Solar + storage project Company LX, Mineral CountySolar + storage · 400 MW · suspended
- Geothermal project Company GW, Mineral CountyGeothermal · 6.0 MW · built
- Solar + storage project Company QS, Mineral CountySolar + storage · 1,500 MW · withdrawn
- Green Borders Geothermal Phase 2Geothermal · 150 MW · withdrawn
- Solar + storage project Company KA, Mineral CountySolar + storage · 100 MW · withdrawn
- Deadhorse Wells Geothermal ProjectGeothermal · 27.0 MW · withdrawn
- Geothermal project Company HC, Mineral CountyGeothermal · 25.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem