Solar project Company GK, Churchill County

Solar project Company GK, Churchill County is a 20.0 MW solar request built and operating in the West interconnection queue, in Churchill County, Nevada, connecting to NV Energy.

Queue statusOperating
  1. PlanningQueued Mar 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingTarget Apr 2018 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
Company GK
Grid region
West (non-ISO utilities)
Utility / transmission owner
NV Energy
Location
Churchill County, Nevada
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
NRIS and ERIS
Study phase
IA Executed
Queue status
Operational
Entered queue
16 March 2015
Proposed online date
April 2018

Location

Marker shows the centre of Churchill County; the queue data does not give exact sites.

Power plants in Nevada · Transmission lines in Nevada

Other requests in Churchill County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem