SOLAR · WESTSolar project 660, Jackson County
Solar project 660, Jackson County is a 10.0 MW solar request built and operating in the West interconnection queue, in Jackson County, Oregon, connecting to PacifiCorp.
Request details
- Queue ID
- 660
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- PacifiCorp
- Developer
- OR Solar 2, LLC
- Connection point (POI)
- Circuit 4R1, Salmon out of Dodge Bridge substation
- Location
- Jackson County, Oregon
- Technology
- Solar: 10.0 MW
- Total requested
- 10.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA signed 2/3/16
- Queue status
- Operational
- Entered queue
- 23 April 2015
- Agreement signed
- 3 February 2016
- Proposed online date
- October 2020
Location
Marker shows the centre of Jackson County; the queue data does not give exact sites.
Other requests in Jackson County
- Other project 151, Jackson CountyOther · 30.0 MW · built
- Solar project 578, Jackson CountySolar · 10.0 MW · built
- Other project 194, Jackson CountyOther · 2.9 MW · built
- Battery storage project C3-175, Jackson CountyBattery storage · 250 MW · withdrawn
- Battery storage project C4-017, Jackson CountyBattery storage · 250 MW · withdrawn
- Solar project 845, Jackson CountySolar · 40.0 MW · withdrawn
- Solar project 887, Jackson CountySolar · 13.0 MW · withdrawn
- Solar project 702, Jackson CountySolar · 10.0 MW · withdrawn
- Solar project 567, Jackson CountySolar · 10.0 MW · withdrawn
- Solar project 552, Jackson CountySolar · 10.0 MW · withdrawn
- Solar project 533, Jackson CountySolar · 10.0 MW · withdrawn
- Solar project 682, Jackson CountySolar · 10.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem