Hydro project 177, Lake County

Hydro project 177, Lake County is a 14.0 MW hydro request built and operating in the West interconnection queue, in Lake County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued Jan 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJun 2015 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
177
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Kerr Switchyard
Location
Lake County, Montana
Technology
Hydro: 14.0 MW
Total requested
14.0 MW
Service type
NRIS and ERIS
Study phase
System Impact Study
Queue status
Operational
Entered queue
13 January 2015
Proposed online date
June 2015
Came online
June 2015

Location

Marker shows the centre of Lake County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Lake County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem