Horn Rapids Solar Project

Horn Rapids Solar Project is a 4.0 MW solar + storage request built and operating in the West interconnection queue, in Benton County, Washington, connecting to Energy Northwest (CGS).

Queue statusOperating
  1. PlanningQueued Nov 2015 (completed)
  2. ConsentedJul 2020 (completed)
  3. Construction (completed)
  4. OperatingTarget Nov 2017 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
G0518
Grid region
West (non-ISO utilities)
Utility / transmission owner
Energy Northwest (CGS)
Connection point (POI)
Pole 3401, City of Richland
Location
Benton County, Washington
Technology
Solar: 3.0 MW · Battery: 1.0 MW
Total requested
4.0 MW
Service type
Energy only (ERIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
13 November 2015
Agreement signed
14 July 2020
Proposed online date
November 2017

Location

Marker shows the centre of Benton County; the queue data does not give exact sites.

Power plants in Washington · Transmission lines in Washington

Other requests in Benton County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem