United States › Grid › Interconnection queues › Washington
SOLAR + STORAGE · WESTHorn Rapids Solar Project
Horn Rapids Solar Project is a 4.0 MW solar + storage request built and operating in the West interconnection queue, in Benton County, Washington, connecting to Energy Northwest (CGS).
Request details
- Queue ID
- G0518
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Energy Northwest (CGS)
- Connection point (POI)
- Pole 3401, City of Richland
- Location
- Benton County, Washington
- Technology
- Solar: 3.0 MW · Battery: 1.0 MW
- Total requested
- 4.0 MW
- Service type
- Energy only (ERIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 13 November 2015
- Agreement signed
- 14 July 2020
- Proposed online date
- November 2017
Location
Marker shows the centre of Benton County; the queue data does not give exact sites.
Power plants in Washington · Transmission lines in Washington
Other requests in Benton County
- Solar + storage project G0822, Benton CountySolar + storage · 4,000 MW · in study
- Nuclear project G0998, Benton CountyNuclear · 1,120 MW · in study
- Solar + storage project G0670, Benton CountySolar + storage · 1,000 MW · in study
- Solar + storage project G0688, Benton CountySolar + storage · 1,000 MW · in study
- Solar + storage project G1040, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0932, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G1037, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G1039, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0920, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0933, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G1038, Benton CountySolar + storage · 800 MW · in study
- Solar + storage project G0684, Benton CountySolar + storage · 705 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem