SOLAR · WEST

Solar project 684, Millard County

Solar project 684, Millard County is a 20.0 MW solar request built and operating in the West interconnection queue, in Millard County, Utah, connecting to PacifiCorp.

Queue statusOperating
  1. PlanningQueued Jul 2015 (completed)
  2. ConsentedMar 2016 (completed)
  3. Construction (completed)
  4. OperatingTarget Dec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
684
Grid region
West (non-ISO utilities)
Utility / transmission owner
PacifiCorp
Developer
Pavant Solar III, LLC
Connection point (POI)
Pavant substation
Location
Millard County, Utah
Technology
Solar: 20.0 MW
Total requested
20.0 MW
Service type
Energy only (ERIS)
Study phase
IA signed 3/23/16
Queue status
Operational
Entered queue
8 July 2015
Agreement signed
23 March 2016
Proposed online date
December 2016

Location

Marker shows the centre of Millard County; the queue data does not give exact sites.

Power plants in Utah · Transmission lines in Utah

Other requests in Millard County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem