Solar project 178, Golden Valley County

Solar project 178, Golden Valley County is a 3.0 MW solar request built and operating in the West interconnection queue, in Golden Valley County, Montana, connecting to NorthWestern Energy.

Queue statusOperating
  1. PlanningQueued Jan 2015 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingDec 2016 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
178
Grid region
West (non-ISO utilities)
Utility / transmission owner
NorthWestern Energy
Connection point (POI)
Lavina Substation, Lavina, MT
Location
Golden Valley County, Montana
Technology
Solar: 3.0 MW
Total requested
3.0 MW
Service type
Energy only (ERIS)
Study phase
Feasibility Study System Impact Study Facilities Study
Queue status
Operational
Entered queue
15 January 2015
Proposed online date
December 2016
Came online
December 2016

Location

Marker shows the centre of Golden Valley County; the queue data does not give exact sites.

Power plants in Montana · Transmission lines in Montana

Other requests in Golden Valley County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem