Completed queue projects in Southeast (non-ISO utilities) (2016 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown333,604 MW
Active in queue977 MW11 requests
Agreement signed753 MW8 requests
Withdrawn21225.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

33 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project 14
Gas
1,148 MWOperating FLSoutheast Mar 2016target 2021
Wadley Solar
Solar
170 MWOperating Jefferson, GASoutheast Jul 20162024
Gas project 205
Gas
160 MWOperating Southeast Sep 20162019
Solar project 297, Lincoln County
Solar
150 MWOperating Lincoln, TNSoutheast Jun 2016
Solar project 286, Colbert County
Solar
80.0 MWOperating Colbert, ALSoutheast Mar 2016
Solar project 182
Solar
75.0 MWOperating Southeast Apr 20162019
Solar project 201
Solar
75.0 MWOperating Southeast Sep 20162019
Solar project 194
Solar
75.0 MWOperating Southeast Jun 20162019
Solar project 181
Solar
75.0 MWOperating Southeast Apr 20162019
Solar project 144A, Hamilton County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Hamilton, FLSoutheast May 20162018
Solar project 160, Gilchrist County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Gilchrist, FLSoutheast Dec 20162019
Solar project 152, Columbia County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Columbia, FLSoutheast Jul 20162021
Solar project 148, Columbia County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Columbia, FLSoutheast May 20162020
Solar project 158, Hamilton County
Solar Β· Duke Energy Florida, LLC
74.9 MWOperating Hamilton, FLSoutheast Sep 20162021
Solar project 169, Columbia County
Solar Β· FRP Columbia County Solar, LLC
74.5 MWOperating Columbia, FLSoutheast Dec 20162024
Solar project 174, Gilchrist County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Gilchrist, FLSoutheast Dec 20162024
Solar project 154, Gilchrist County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Gilchrist, FLSoutheast Aug 20162023
Solar project 187
Solar Β· FPL
74.5 MWOperating Southeast Apr 20162020
Solar project 1
Solar
74.5 MWOperating Southeast Aug 20162020
Solar project 194A
Solar Β· FPL
74.5 MWOperating Southeast Aug 20162020
Solar project 200
Solar Β· FPL
74.5 MWOperating Southeast Sep 20162020
Solar project 183
Solar Β· FPL
74.5 MWOperating Southeast Apr 20162020
Solar project 206, Hendry County
Solar Β· FPL
74.5 MWOperating Hendry, FLSoutheast Sep 20162022
Solar project 173, Levy County
Solar Β· Florida Renewable Partners, LLC
74.5 MWOperating Levy, FLSoutheast Dec 20162025
Solar project 203, Brevard County
Solar Β· FPL
74.5 MWOperating Brevard, FLSoutheast Sep 20162021
Solar project 202
Solar Β· FPL
74.5 MWOperating Southeast Sep 20162020
Solar project 17116
Solar Β· Duke Energy Carolinas LLC
70.0 MWOperating Southeast Nov 20162020
Solar project 291, Colbert County
Solar
67.0 MWOperating Colbert, ALSoutheast Apr 2016
Solar project 279, Shelby County
Solar
60.0 MWOperating Shelby, TNSoutheast Feb 2016
Solar project 149, Highlands County
Solar Β· Duke Energy Florida, LLC
45.0 MWOperating Highlands, FLSoutheast Jun 20162019
Nuclear project 174
Nuclear
30.0 MWOperating Southeast Jan 20162018
Nuclear project 175
Nuclear Β· FPL
30.0 MWOperating Southeast Jan 20162020
Solar project 9409
Solar Β· Duke Energy Carolinas LLC
25.0 MWOperating Southeast Nov 20162020

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)