United States βΊ Grid βΊ Interconnection queues
SOLAR Β· SOUTHEASTSolar project 194
Solar project 194 is a 75.0 MW solar request built and operating in the Southeast interconnection queue.
Request details
- Queue ID
- 194
- Grid region
- Southeast (non-ISO utilities)
- Connection point (POI)
- Davis-Florida City #2 138kV
- Technology
- Solar: 75.0 MW
- Total requested
- 75.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Operational
- Queue status
- Operational
- Entered queue
- 16 June 2016
- Came online
- January 2019
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem