United States β€Ί Grid β€Ί Interconnection queues β€Ί Florida

GAS Β· SOUTHEAST

Gas project 14

Gas project 14 is a 1,148 MW gas request built and operating in the Southeast interconnection queue, connecting to Seminole Electric Cooperative.

Queue statusOperating
  1. PlanningQueued Mar 2016 (completed)
  2. ConsentedNov 2017 (completed)
  3. Construction (completed)
  4. OperatingTarget Jun 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
14
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Seminole Electric Cooperative
Connection point (POI)
SGS Switchyard
Location
Florida
Technology
Gas: 1,148 MW
Total requested
1,148 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: System Impact; Status: Completed and unit in-service.
Queue status
Operational
Entered queue
9 March 2016
Agreement signed
13 November 2017
Proposed online date
June 2021

Location

No county location in the queue data.

Power plants in Florida Β· Transmission lines in Florida

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem