United States βΊ Grid βΊ Interconnection queues
SOLAR Β· SOUTHEASTSolar project 9409
Solar project 9409 is a 25.0 MW solar request built and operating in the Southeast interconnection queue.
Request details
- Queue ID
- 9409
- Grid region
- Southeast (non-ISO utilities)
- Developer
- Duke Energy Carolinas LLC
- Connection point (POI)
- Willow
- Technology
- Solar: 25.0 MW
- Total requested
- 25.0 MW
- Study phase
- Commercial Operation - Commercial Operation Date Declared
- Queue status
- Operational
- Entered queue
- 16 November 2016
- Proposed online date
- November 2020
- Came online
- November 2020
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem