πŸ”Œ EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more β†’ Skip to main content

United States β€Ί Grid β€Ί Interconnection queues

SOLAR Β· SOUTHEAST

Solar project 187

Solar project 187 is a 74.5 MW solar request built and operating in the Southeast interconnection queue, connecting to Florida Power & Light.

Queue statusOperating
  1. PlanningQueued Apr 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingJan 2020 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
187
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Sunshine Sub
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
Network resource (NRIS)
Study phase
IA Executed
Queue status
Operational
Entered queue
18 April 2016
Came online
January 2020

Location

Marker shows the centre of County; the queue data does not give exact sites.

Power plants in Β· Transmission lines in

Other requests in County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem