United States › Grid › Interconnection queues › Florida

SOLAR · SOUTHEAST

Solar project 173, Levy County

Solar project 173, Levy County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Levy County, Florida, connecting to Duke Energy Florida.

Queue statusOperating
  1. PlanningQueued Dec 2016 (completed)
  2. Consented (completed)
  3. Construction (completed)
  4. OperatingSep 2025 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
173
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Duke Energy Florida
Developer
Florida Renewable Partners, LLC
Connection point (POI)
Bronson Substation
Location
Levy County, Florida
Technology
Solar: 74.5 MW
Total requested
74.5 MW
Service type
NRIS and ERIS
Study phase
IA Executed
Queue status
Operational
Entered queue
21 December 2016
Proposed online date
June 2021
Came online
September 2025

Location

Marker shows the centre of Levy County; the queue data does not give exact sites.

Power plants in Florida · Transmission lines in Florida

Other requests in Levy County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem