United States βΊ Grid βΊ Interconnection queues
SOLAR Β· SOUTHEASTSolar project 200
Solar project 200 is a 74.5 MW solar request built and operating in the Southeast interconnection queue, connecting to Florida Power & Light.
Request details
- Queue ID
- 200
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Wiremill Tap
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 19 September 2016
- Came online
- January 2020
Location
Marker shows the centre of County; the queue data does not give exact sites.
Other requests in County
- Solar project 344, Baker CountySolar Β· 74.5 MW Β· in study
- Solar project 376, Baker CountySolar Β· 74.5 MW Β· in study
- Solar project 375, Baker CountySolar Β· 74.5 MW Β· built
- Solar project 300, Baker CountySolar Β· 74.5 MW Β· built
- Solar project 374, Baker CountySolar Β· 74.5 MW Β· built
- Solar project 212, Baker CountySolar Β· 60.0 MW Β· withdrawn
- Solar project 421, Baker CountySolar Β· 14.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem