SOLAR Β· SOUTHEAST

Solar project 212, Baker County

Solar project 212, Baker County is a 60.0 MW solar request withdrawn in the Southeast interconnection queue, in Baker County, Florida, connecting to Florida Power & Light.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Oct 2016 (completed)
  2. Withdrawn / abandoned (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
212
Grid region
Southeast (non-ISO utilities)
Utility / transmission owner
Florida Power & Light
Developer
FPL
Connection point (POI)
Raven-Macedonia (GTC) 115kV
Location
Baker County, Florida
Technology
Solar: 60.0 MW
Total requested
60.0 MW
Service type
Network resource (NRIS)
Study phase
Facility Study
Queue status
Withdrawn
Entered queue
14 October 2016
Proposed online date
October 2025

Location

Marker shows the centre of Baker County; the queue data does not give exact sites.

Power plants in Florida Β· Transmission lines in Florida

Other requests in Baker County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem