United States βΊ Grid βΊ Interconnection queues βΊ Florida
SOLAR Β· SOUTHEASTSolar project 212, Baker County
Solar project 212, Baker County is a 60.0 MW solar request withdrawn in the Southeast interconnection queue, in Baker County, Florida, connecting to Florida Power & Light.
Queue statusWithdrawn / abandoned
- PlanningQueued Oct 2016 (completed)
- Withdrawn / abandoned (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 212
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Raven-Macedonia (GTC) 115kV
- Location
- Baker County, Florida
- Technology
- Solar: 60.0 MW
- Total requested
- 60.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Facility Study
- Queue status
- Withdrawn
- Entered queue
- 14 October 2016
- Proposed online date
- October 2025
Location
Marker shows the centre of Baker County; the queue data does not give exact sites.
Other requests in Baker County
- Solar project 344, Baker CountySolar Β· 74.5 MW Β· in study
- Solar project 376, Baker CountySolar Β· 74.5 MW Β· in study
- Solar project 375, Baker CountySolar Β· 74.5 MW Β· built
- Solar project 300, Baker CountySolar Β· 74.5 MW Β· built
- Solar project 200Solar Β· 74.5 MW Β· built
- Solar project 374, Baker CountySolar Β· 74.5 MW Β· built
- Solar project 421, Baker CountySolar Β· 14.5 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem