SOLAR · SOUTHEASTSolar project 375, Baker County
Solar project 375, Baker County is a 74.5 MW solar request built and operating in the Southeast interconnection queue, in Baker County, Florida, connecting to Florida Power & Light.
Request details
- Queue ID
- 375
- Grid region
- Southeast (non-ISO utilities)
- Utility / transmission owner
- Florida Power & Light
- Developer
- FPL
- Connection point (POI)
- Duval-Raven 230kV
- Location
- Baker County, Florida
- Technology
- Solar: 74.5 MW
- Total requested
- 74.5 MW
- Service type
- Network resource (NRIS)
- Study phase
- IA Executed
- Queue status
- Operational
- Entered queue
- 22 November 2019
- Proposed online date
- November 2024
- Came online
- November 2024
Location
Marker shows the centre of Baker County; the queue data does not give exact sites.
Other requests in Baker County
- Solar project 344, Baker CountySolar · 74.5 MW · in study
- Solar project 376, Baker CountySolar · 74.5 MW · in study
- Solar project 300, Baker CountySolar · 74.5 MW · built
- Solar project 200Solar · 74.5 MW · built
- Solar project 374, Baker CountySolar · 74.5 MW · built
- Solar project 212, Baker CountySolar · 60.0 MW · withdrawn
- Solar project 421, Baker CountySolar · 14.5 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem