United States β€Ί Grid β€Ί Interconnection queues β€Ί New Mexico

OCTARY USA Β· INTERCONNECTION QUEUES

Interconnection queue in New Mexico, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown4710.3 GW
Active in queue10.3 GW47 requests
Agreement signed1,566 MW8 requests
Withdrawn14529.1 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

47 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2020-065, Gaines County
Gas
1,003 MWAgreement signed Gaines, NMSPP Apr 2020target 2028
Solar + storage project GEN-2024-073, Lea County
Solar + storage
500 MWIn study Lea, NMSPP Oct 2024target 2028
Solar + storage project GEN-2024-303, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-304, Roosevelt County
Solar + storage
500 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-124, Lea County
Solar + storage
420 MWIn study Lea, NMSPP Mar 2025target 2028
Solar + storage project ERAS-2025-020, Lea County
Solar + storage
400 MWIn study Lea, NMSPP Oct 2025target 2030
Onshore wind project GEN-2024-221, Roosevelt County
Onshore wind
400 MWIn study Roosevelt, NMSPP Mar 2025target 2030
Solar + storage project ERAS-2025-030, Chaves County
Solar + storage
350 MWIn study Chaves, NMSPP Oct 2025target 2030
Solar project GEN-2024-159, Roosevelt County
Solar
300 MWIn study Roosevelt, NMSPP Mar 2025target 2029
Wind + storage project GEN-2024-278, Lea County
Wind + storage
264 MWIn study Lea, NMSPP Mar 2025target 2029
Solar + storage project ERAS-2025-018, Roosevelt County
Solar + storage
256 MWIn study Roosevelt, NMSPP Oct 2025target 2030
Solar project GEN-2024-079, Curry County
Solar
250 MWIn study Curry, NMSPP Oct 2024target 2029
Solar project GEN-2024-080, Curry County
Solar
250 MWIn study Curry, NMSPP Oct 2024target 2029
Onshore wind project GEN-2024-043, Roosevelt County
Onshore wind
250 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Solar + storage project GEN-2024-271, Chaves County
Solar + storage
250 MWIn study Chaves, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-281, Lea County
Solar + storage
250 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-371, Lea County
Battery storage
250 MWIn study Lea, NMSPP Mar 2025target 2028
Solar project GEN-2024-311, Chaves County
Solar
225 MWIn study Chaves, NMSPP Mar 2025target 2030
Onshore wind project GEN-2024-365, Lea County
Onshore wind
200 MWIn study Lea, NMSPP Mar 2025target 2030
Onshore wind project GEN-2024-366, Lea County
Onshore wind
200 MWIn study Lea, NMSPP Mar 2025target 2030
Battery storage project GEN-2024-092, Roosevelt County
Battery storage
200 MWIn study Roosevelt, NMSPP Oct 2024target 2029
Battery storage project GEN-2024-246, Eddy County
Battery storage
199 MWIn study Eddy, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-351, Lea County
Solar + storage
199 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-186, Chaves County
Battery storage
199 MWIn study Chaves, NMSPP Mar 2025target 2029
Solar project GEN-2024-GR3, Lea County
Solar
196 MWIn study Lea, NMSPP Jun 2024target 2027
Onshore wind project GEN-2024-089, Curry County
Onshore wind
195 MWIn study Curry, NMSPP Oct 2024target 2029
Battery storage project GEN-2024-324, Chaves County
Battery storage
160 MWIn study Chaves, NMSPP Mar 2025target 2028
Gas project ERAS-2025-014, Lea County
Gas
160 MWIn study Lea, NMSPP Oct 2025target 2029
Solar + storage project GEN-2024-265, Lea County
Solar + storage
155 MWIn study Lea, NMSPP Mar 2025target 2029
Solar + storage project GEN-2024-261, Lea County
Solar + storage
150 MWIn study Lea, NMSPP Mar 2025target 2029
Battery storage project GEN-2024-325, Chaves County
Battery storage
150 MWIn study Chaves, NMSPP Mar 2025target 2028
Solar project GEN-2019-003, Roosevelt County
Solar
150 MWAgreement signed Roosevelt, NMSPP Apr 2019target 2027
Battery storage project GEN-2024-306, Lea County
Battery storage
150 MWIn study Lea, NMSPP Mar 2025target 2031
Battery storage project GEN-2024-251, Eddy County
Battery storage
125 MWIn study Eddy, NMSPP Mar 2025target 2029
Onshore wind project GEN-2025-GR2, Roosevelt County
Onshore wind
120 MWIn study Roosevelt, NMSPP Jun 2025
Battery storage project GEN-2024-295, Eddy County
Battery storage
115 MWIn study Eddy, NMSPP Mar 2025target 2030
Solar project GEN-2016-121, Lea County
Solar
110 MWAgreement signed Lea, NMSPP Nov 2016target 2026
Battery storage project GEN-2024-310, Chaves County
Battery storage
75.0 MWIn study Chaves, NMSPP Mar 2025target 2030
Solar project GEN-2018-004, Lea County
Solar
75.0 MWAgreement signed Lea, NMSPP Apr 2018target 2027
Battery storage project GEN-2025-SR29, Lea County
Battery storage
75.0 MWIn study Lea, NMSPP Aug 2025target 2027
Solar project GEN-2023-GR4, Lea County
Solar
72.0 MWAgreement signed Lea, NMSPP Jul 2023target 2026
Battery storage project GEN-2018-052, Lea County
Battery storage
70.0 MWAgreement signed Lea, NMSPP May 2018target 2026
Battery storage project GEN-2025-SR32, Chaves County
Battery storage
50.0 MWIn study Chaves, NMSPP Oct 2025target 2026
Solar project GEN-2019-021, Roosevelt County
Solar
50.0 MWAgreement signed Roosevelt, NMSPP Apr 2019target 2027
Battery storage project GEN-2025-SR27, Chaves County
Battery storage
50.0 MWIn study Chaves, NMSPP Jul 2025target 2026
Battery storage project GEN-2024-SR14, Lea County
Battery storage
36.0 MWAgreement signed Lea, NMSPP Jul 2024target 2026
Solar project GEN-2024-273, Lea County
Solar
16.2 MWIn study Lea, NMSPP Mar 2025target 2026

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)