Queue requests in study in Nebraska, SPP

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5611.4 GW
Active in queue16.2 GW84 requests
Agreement signed4,803 MW28 requests
Withdrawn23939.6 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

56 requests Β· page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Gas project GEN-2024-021, Lancaster County
Gas
540 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2023-222, Gage County
Gas
478 MWIn study Gage, NESPP Oct 2023target 2030
Gas project GEN-2023-224, Lancaster County
Gas
478 MWIn study Lancaster, NESPP Oct 2023target 2029
Gas project GEN-2024-020, Lancaster County
Gas
390 MWIn study Lancaster, NESPP Oct 2024target 2030
Gas project GEN-2024-022, Gage County
Gas
390 MWIn study Gage, NESPP Oct 2024target 2030
Gas project GEN-2024-213, Cass County
Gas
360 MWIn study Cass, NESPP Mar 2025target 2035
Solar + storage project GEN-2020-011, Phelps County
Solar + storage
320 MWIn study Phelps, NESPP Apr 2020target 2028
Solar project GEN-2017-210, Cedar County
Solar
310 MWPaused / redesign Cedar, NESPP Nov 2017target 2026
Gas project GEN-2024-211, Cass County
Gas
303 MWIn study Cass, NESPP Mar 2025target 2035
Gas project GEN-2024-212, Cass County
Gas
303 MWIn study Cass, NESPP Mar 2025target 2035
Solar project GEN-2024-038, Nemaha County
Solar
300 MWIn study Nemaha, NESPP Oct 2024target 2029
Onshore wind project GEN-2021-057, Antelope County
Onshore wind
300 MWIn study Antelope, NESPP Apr 2021target 2027
Gas project GEN-2023-079, Cass County
Gas
273 MWIn study Cass, NESPP Oct 2023target 2032
Gas project GEN-2024-023, Gage County
Gas
270 MWIn study Gage, NESPP Oct 2024target 2030
Gas project GEN-2023-077, Cass County
Gas
255 MWIn study Cass, NESPP Oct 2023target 2028
Gas project GEN-2023-078, Cass County
Gas
255 MWIn study Cass, NESPP Oct 2023target 2028
Solar project GEN-2024-140, Douglas County
Solar
250 MWIn study Douglas, NESPP Mar 2025target 2033
Solar project GEN-2024-039, Nemaha County
Solar
250 MWIn study Nemaha, NESPP Oct 2024target 2029
Solar + storage project GEN-2023-199, Dakota County
Solar + storage
250 MWIn study Dakota, NESPP Oct 2023target 2027
Battery storage project GEN-2024-372, Douglas County
Battery storage
250 MWIn study Douglas, NESPP Mar 2025target 2028
Gas project GEN-2023-223, Gage County
Gas
239 MWIn study Gage, NESPP Oct 2023target 2030
Solar project GEN-2024-374, Scotts Bluff County
Solar
225 MWIn study Scotts Bluff, NESPP Mar 2025target 2030
Gas project GEN-2023-225, Lancaster County
Gas
217 MWIn study Lancaster, NESPP Oct 2023target 2029
Solar + storage project GEN-2020-013, Harlan County
Solar + storage
215 MWIn study Harlan, NESPP Apr 2020target 2027
Other project GEN-2025-SR24, Washington County
Other
200 MWIn study Washington, NESPP Jun 2025target 2028
Other project GEN-2025-SR26, Cass County
Other
200 MWIn study Cass, NESPP Jun 2025target 2029
Solar project GEN-2024-234, Burt County
Solar
200 MWIn study Burt, NESPP Mar 2025target 2029
Battery storage project GEN-2018-025, Washington County
Battery storage
200 MWPaused / redesign Washington, NESPP May 2018target 2028
Battery storage project GEN-2024-173, Lancaster County
Battery storage
200 MWIn study Lancaster, NESPP Mar 2025target 2028
Battery storage project GEN-2018-033, Cass County
Battery storage
200 MWPaused / redesign Cass, NESPP May 2018target 2029
Solar project GEN-2024-168, Fillmore County
Solar
200 MWIn study Fillmore, NESPP Mar 2025target 2033
Battery storage project GEN-2021-040, Cass County
Battery storage
200 MWIn study Cass, NESPP Apr 2021target 2029
Solar project GEN-2021-108, Cass County
Solar
182 MWIn study Cass, NESPP May 20212025
Solar project GEN-2024-040, Nemaha County
Solar
174 MWIn study Nemaha, NESPP Oct 2024target 2029
Battery storage project GEN-2024-051, Lancaster County
Battery storage
170 MWIn study Lancaster, NESPP Oct 2024target 2028
Battery storage project GEN-2025-SR31, Madison County
Battery storage
170 MWIn study Madison, NESPP Nov 2025target 2026
Battery storage project GEN-2024-065, Dodge County
Battery storage
150 MWIn study Dodge, NESPP Oct 2024target 2029
Battery storage project GEN-2023-SR7, Wayne County
Battery storage
135 MWIn study Wayne, NESPP Dec 20222024
Solar + storage project GEN-2023-153, Perkins County
Solar + storage
120 MWIn study Perkins, NESPP Oct 2023target 2028
Solar + storage project GEN-2024-162, Dakota County
Solar + storage
110 MWIn study Dakota, NESPP Mar 2025target 2030
Gas project ERAS-2025-001, Lancaster County
Gas
104 MWIn study Lancaster, NESPP Sep 2025target 2029
Solar project GEN-2021-027, Lancaster County
Solar
102 MWIn study Lancaster, NESPP May 2021target 2026
Solar project GEN-2019-009, Nemaha County
Solar
100 MWPaused / redesign Nemaha, NESPP Apr 2019target 2029
Battery storage project GEN-2021-039, Douglas County
Battery storage
100 MWIn study Douglas, NESPP Apr 2021target 2030
Other project GEN-2025-SR20, Douglas County
Other
100 MWIn study Douglas, NESPP Jun 2025target 2030
Battery storage project GEN-2018-037, Douglas County
Battery storage
100 MWPaused / redesign Douglas, NESPP May 2018target 2030
Battery storage project GEN-2024-SR10, Lancaster County
Battery storage
80.0 MWIn study Lancaster, NESPP Apr 2024target 2026
Solar project GEN-2019-041, Lancaster County
Solar
78.0 MWPaused / redesign Lancaster, NESPP May 2019target 2028
Battery storage project GEN-2024-SR8, Greeley County
Battery storage
70.0 MWIn study Greeley, NESPP Apr 2024target 2026
Other project GEN-2024-231, Richardson County
Other
65.0 MWIn study Richardson, NESPP Mar 2025target 2029
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)