United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Projects with signed interconnection agreements in PJM (Mid-Atlantic, Midwest) (2019 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12311.3 GW
Active in queue19.2 GW183 requests
Agreement signed11.3 GW123 requests
Withdrawn40938.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

123 requests Β· page 1 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Chesterfield CT Units 3&4
Gas
569 MWAgreement signed Chesterfield, VAPJM Sep 2019target 2029
Randolph Solar
Solar Β· Virginia Electric and Power Company (d/b/a Dominion Energy Virginia)
500 MWAgreement signed Halifax, VAPJM Dec 2019target 2032
Yellow Wood Solar Energy Center
Solar
300 MWAgreement signed Clinton, OHPJM Mar 2019target 2026
Cassius Blue Solar
Solar + storage
300 MWAgreement signed Sussex, VAPJM Feb 2019target 2031
Eastern Cottontail Solar
Solar
220 MWAgreement signed Fairfield, OHPJM Jan 2019target 2028
Prospect Power
Battery storage
200 MWAgreement signed Rockingham, VAPJM May 2019target 2026
Flint Grid
Battery storage
200 MWAgreement signed Licking, OHPJM Jul 2019target 2027
Black Prairie Solar Park
Solar
200 MWAgreement signed White, INPJM Sep 2019target 2027
Bottlebrush Solar
Solar
200 MWAgreement signed Lake, INPJM Jan 2019target 2028
Blackford Wind Energy Project
Onshore wind
200 MWAgreement signed Blackford, INPJM Sep 2019target 2026
Pleasant Prairie Solar Energy Center
Solar
200 MWAgreement signed Franklin, OHPJM Mar 2019target 2027
Hudson Energy Storage Facility
Battery storage
200 MWAgreement signed Hudson, NJPJM Sep 2019target 2028
Lynn Bark Energy Center
Solar
200 MWAgreement signed Martin, KYPJM Nov 2019target 2029
Rolling Farms Wind Project
Onshore wind
200 MWAgreement signed Christian, ILPJM Aug 2019target 2029
Lake Trout Solar
Solar + storage
200 MWAgreement signed Blackford, INPJM Sep 2019target 2028
CG Fulton County
Solar
199 MWAgreement signed Fulton, OHPJM Sep 2019target 2028
Fleming Solar
Solar Β· AEUG Fleming Solar, LLC
189 MWAgreement signed Fleming, KYPJM Sep 2019target 2029
Hoosier Line Solar
Solar
180 MWAgreement signed White, INPJM Sep 2019target 2027
Sculpin Solar
Solar
180 MWAgreement signed Dekalb, INPJM Aug 2019target 2028
Sloopy Solar Energy Center
Solar
180 MWAgreement signed Clark, OHPJM Mar 2019target 2028
Lamberton Road Battery
Battery storage
170 MWAgreement signed Mercer, NJPJM Sep 2019target 2027
Skycrest Solar Energy Center
Solar
155 MWAgreement signed Jay, INPJM Feb 2019target 2026
Springwater Solar
Solar
155 MWAgreement signed Madison, OHPJM Sep 2019target 2027
Blackford Solar Energy Project
Solar
150 MWAgreement signed Jay, INPJM Sep 2019target 2026
Wild Grains Solar
Solar
150 MWAgreement signed Van Wert, OHPJM Oct 2019target 2027
Heritage Prairie Solar
Solar
150 MWAgreement signed Kankakee, ILPJM Mar 2019target 2027
Big Pine Solar
Solar
150 MWAgreement signed Sussex, VAPJM Feb 2019target 2031
Woodridge Solar
Solar
138 MWAgreement signed Albemarle, VAPJM Feb 2019target 2027
Highland 3 Solar
Solar
130 MWAgreement signed Highland, OHPJM Sep 2019target 2030
Riverstart Solar Park II
Solar
125 MWAgreement signed Randolph, INPJM Mar 2019target 2027
Southern Virginia Solar
Solar
125 MWAgreement signed Pittsylvania, VAPJM Jul 2019target 2027
Tymochtee Solar
Solar
120 MWAgreement signed Wyandot, OHPJM Sep 2019target 2026
Ridgeway Solar
Solar
120 MWAgreement signed Mckean, PAPJM Mar 2019target 2026
Appalachian Cottontail Solar
Solar
114 MWAgreement signed Fairfield, OHPJM Mar 2019target 2028
Hoodlebug Solar Energy Center
Solar
110 MWAgreement signed Indiana, PAPJM Oct 2019target 2027
Rogue's Wind
Onshore wind
110 MWAgreement signed Clearfield, PAPJM Aug 2019target 2026
Hillandale Solar
Solar Β· Hillandale Solar, LLC
102 MWAgreement signed Pittsylvania, VAPJM Mar 2019target 2030
Bradford Solar
Solar
101 MWAgreement signed Mckean, PAPJM Mar 2019target 2027
Panther Grove 2
Onshore wind
100 MWAgreement signed Woodford, ILPJM Mar 2019target 2027
Elkhart County Solar Project
Solar
100 MWAgreement signed Elkhart, INPJM Mar 2019target 2026
Gibson Solar I
Solar
100 MWAgreement signed King George, VAPJM Sep 2019target 2027
Harwood Power
Battery storage
100 MWAgreement signed King George, VAPJM Oct 2019target 2029
Nuthatch Solar 5
Solar
100 MWAgreement signed Highland, OHPJM Sep 2019target 2030
Rockdale Solar
Solar
100 MWAgreement signed Somerset, PAPJM Sep 2019target 2028
Scioto Solar
Solar + storage
100 MWAgreement signed Hardin, OHPJM Oct 2019target 2026
Threeforks Energy Storage
Battery storage
100 MWAgreement signed Martin, KYPJM Sep 2019target 2028
Blue Rock Solar
Solar
100 MWAgreement signed Buckingham, VAPJM Mar 2019target 2026
Dulles Solar and BESS
Solar
100 MWAgreement signed Loudoun, VAPJM Sep 2019target 2026
Rippon
Solar
99.0 MWAgreement signed Jefferson, WVPJM Mar 2019target 2026
Cassius Blue Solar
Solar + storage
94.0 MWAgreement signed Sussex, VAPJM Aug 2019target 2031
Page 1 of 3

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)